5934 N NOBLE AVE 91411
Certificate Information: 5934 N NOBLE AVE 91411
- Application / Permit
- 20016-20000-06520
- Plan Check / Job No.
- B20VN03923
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- CHANGE OF USE FROM MANUFACTURING BUILDING TO INDOOR NURSERY & MANUFACTURING . NEW OPENING FOR INTERIOR ACCESS BETWEEN ADJOINING BUILDING. Comply with the Department order issued on 8/15/2019
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | ALBERT SERVIN |
| Disabled Access Plans Picked Up | 3/19/2020 | APPLICANT |
| Corrections Issued | 3/23/2020 | RUDOLF KINAR MELIKOFF |
| Quality Review Completed | 3/24/2020 | STEVEN KIM |
| Building Plans Picked Up | 4/6/2020 | APPLICANT |
| Green Plans Picked Up | 4/6/2020 | APPLICANT |
| Applicant returned to address corrections | 9/14/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 10/6/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 11/4/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 11/5/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 2/10/2021 | ALBERT SERVIN |
| Plan Check Approved | 3/12/2021 | ALBERT SERVIN |
| Issued | 4/12/2021 | APPLICANT |
| TCO Issued (Expire Date: 04-03-2024) | 10/6/2023 | JEFFREY DURAN |
| CofO in Progress | 2/20/2024 | CAMERON CHABAN |
| Permit Finaled | 3/6/2024 | JEFFREY DURAN |
| CofO Issued | 3/6/2024 | JEFFREY DURAN |
| Permit Finaled | 3/6/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Green Code | Cleared | 8/20/2020 | MICHAEL AYERS |
| Green Code | Cleared | 8/20/2020 | RUDOLF KINAR MELIKOFF |
| Address approval | Cleared | 8/26/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/26/2020 | JOHN TRIANTAFYLLOS |
| DAS Clearance | Cleared | 8/27/2020 | NORLITO MEDRANO |
| DAS Clearance | Cleared | 8/27/2020 | RUDOLF KINAR MELIKOFF |
| Fire Marshall Fire Life Safety | Cleared | 11/10/2020 | VIDAL GARCIA |
| Hydrant and Access approval | Cleared | 12/10/2020 | MATTHEW CRAIG |
Contact Information
| Contractor | Cromewell Construction Inc; Lic. No.: 1042115-B | 530 SOUTH LAKE AVE #588 PASADENA, CA 91101 |
| Engineer | Boros,, Janos; Lic. No.: C54869 | 14189 FOOTHILL BLVD STE 101 FONTANA, CA 92335 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 5/19/2021 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 1/18/2022 | Partial Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 1/25/2022 | Conditional Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 1/28/2022 | Partial Approval | CAMERON CHABAN |
| Interior/Exterior Lathing | 2/2/2022 | Partial Approval | CAMERON CHABAN |
| Wood Frame | 4/5/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Drilled-In Anchors | 6/1/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 6/9/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 7/15/2022 | Conditional Approval | CAMERON CHABAN |
| Insulation | 7/15/2022 | Approved | CAMERON CHABAN |
| Drywall Nailing | 7/21/2022 | Approved | CAMERON CHABAN |
| Excavation/Setback/Form/Re-Bar | 2/9/2023 | Conditional Approval | CAMERON CHABAN |
| Final | 9/28/2023 | Partial Inspection | CAMERON CHABAN |
| Green Building Final | 9/28/2023 | Partial Inspection | CAMERON CHABAN |
| Green Building Rough | 9/28/2023 | Approved | CAMERON CHABAN |
| METHANE-Final | 9/28/2023 | Approved | CAMERON CHABAN |
| METHANE-Rough | 9/28/2023 | Approved | CAMERON CHABAN |
| Reinforced Masonry Frame | 9/28/2023 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV No Gas | CAMERON CHABAN |
| Smoke Detectors | 9/28/2023 | Approved | CAMERON CHABAN |
| Final | 1/31/2024 | Partial Inspection | CAMERON CHABAN |
| Green Building Final | 1/31/2024 | Approved | CAMERON CHABAN |
| Final | 2/9/2024 | Partial Inspection | CAMERON CHABAN |
| Final | 2/20/2024 | OK to Issue CofO | CAMERON CHABAN |
| Special/Order Compliance | 3/5/2024 | Not Ready for Inspection | BRIAN KELLY |