7755 N VINELAND AVE 91352

Certificate Information: 7755 N VINELAND AVE 91352

Application / Permit
20016-20000-06516
Plan Check / Job No.
B20VN03918
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'-2" x 20'-2" DET. GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 5/28/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/6/2020 RAPHAEL ROSAS
Corrections Issued 3/8/2020 RAPHAEL ROSAS
Plan Check Approved 3/16/2020 RAPHAEL ROSAS
Issued 5/28/2020 LADBS
Building Plans Picked Up 6/2/2020 APPLICANT
CofO in Progress 9/15/2020 DAVID MATSON
Permit Finaled 9/23/2020 MICHAEL SMITH
CofO Issued 9/23/2020 MICHAEL SMITH
Permit Finaled 9/23/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/10/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 3/10/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 3/10/2020 GUILLERMO PETRA
Sewer availability Cleared 3/10/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/10/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 6/10/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 6/12/2020 Approved JOHN HAYES
PLUMBING-Rough 6/12/2020 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 6/18/2020 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 6/18/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 6/18/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 6/18/2020 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 6/18/2020 Partial Approval PIERRE VEGA
BUILDING-Rough-Frame 6/22/2020 Approved JOHN HAYES
Green Building Rough 6/22/2020 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 6/22/2020 Approved JOHN HAYES
Insulation 6/24/2020 Approved JOHN HAYES
Interior/Exterior Lathing 6/24/2020 Approved JOHN HAYES
Drywall Nailing 6/29/2020 Approved PIERRE VEGA
ELECTRICAL-Final 7/28/2020 Corrections Issued MATTHEW NELSON
Final 7/28/2020 Corrections Issued MATTHEW NELSON
Green Building Final 7/28/2020 Corrections Issued MATTHEW NELSON
HVAC-Final 7/28/2020 Corrections Issued MATTHEW NELSON
PLUMBING-Final 7/28/2020 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/28/2020 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 7/28/2020 Corrections Issued MATTHEW NELSON
ELECTRICAL-Final 7/29/2020 Not Ready for Inspection JOHN HAYES
Final 7/29/2020 Corrections Issued JOHN HAYES
HVAC-Final 7/29/2020 Not Ready for Inspection JOHN HAYES
Pre-Inspection 7/29/2020 Not Ready for Inspection JOHN HAYES
Final 9/14/2020 OK to Issue CofO DAVID MATSON
Green Building Final 9/14/2020 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 9/14/2020 SGSOV Approved DAVID MATSON
Smoke Detectors 9/14/2020 Approved DAVID MATSON
Special/Order Compliance 9/14/2020 Approved DAVID MATSON