20931 W HEMMINGWAY ST 91304

Certificate Information: 20931 W HEMMINGWAY ST 91304

Application / Permit
20016-20000-06416
Plan Check / Job No.
B20VN03852
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 22' 4" X 21' DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 5/28/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/4/2020 JEFFREY TANGONAN
Corrections Issued 3/4/2020 JEFFREY TANGONAN
Building Plans Picked Up 3/9/2020 APPLICANT
Plan Check Approved 5/7/2020 GURUNATH NESARAJAH
Issued 5/28/2020 LADBS
CofO in Progress 11/25/2021 STEVEN BACK
CofO in Progress 11/25/2021 STEVEN BACK
Permit Finaled 11/30/2021 JOHN JANSON
CofO Issued 11/30/2021 JOHN JANSON
Permit Finaled 11/30/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/9/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/9/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 4/23/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 5/1/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/15/2020 Approved HENRY KIM
Underground Mechanical 9/15/2020 Corrections Issued HENRY KIM
PLUMBING-Rough 10/6/2020 Partial Approval HENRY KIM
Green Building Rough 10/30/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 1/22/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 1/22/2021 Corrections Issued HENRY KIM
Green Building Rough 1/22/2021 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 1/22/2021 Corrections Issued HENRY KIM
Special/Order Compliance 2/5/2021 Approved HENRY KIM
Special/Order Compliance 4/12/2021 Approved HENRY KIM
ELECTRICAL-Rough 4/26/2021 Corrections Issued HENRY KIM
Insulation 4/26/2021 Partial Approval HENRY KIM
PLUMBING-Rough 4/26/2021 Approved HENRY KIM
ELECTRICAL-Rough 5/4/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Approved HENRY KIM
Footing/Foundation/Slab 5/4/2021 Not Ready for Inspection HENRY KIM
Insulation 5/4/2021 Partial Approval HENRY KIM
Interior/Exterior Lathing 5/4/2021 Corrections Issued HENRY KIM
Sewer 5/4/2021 Corrections Issued HENRY KIM
Underground Mechanical 5/4/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 5/10/2021 Approved HENRY KIM
Insulation 5/10/2021 Corrections Issued HENRY KIM
Interior/Exterior Lathing 5/10/2021 Approved HENRY KIM
Underground Mechanical 5/10/2021 Partial Approval HENRY KIM
BUILDING-Rough-Frame 5/13/2021 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Corrections Issued HENRY KIM
Green Building Rough 5/13/2021 Approved HENRY KIM
Insulation 5/13/2021 Approved HENRY KIM
Sewer 5/13/2021 Approved HENRY KIM
Underground Mechanical 5/13/2021 Approved HENRY KIM
BUILDING-Rough-Frame 5/17/2021 Approved HENRY KIM
Drywall Nailing 5/17/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/17/2021 Approved HENRY KIM
Green Building Final 5/26/2021 Partial Approval HENRY KIM
ELECTRICAL-Final 7/12/2021 Corrections Issued HENRY KIM
Final 7/12/2021 Corrections Issued HENRY KIM
Gas Test 7/12/2021 Corrections Issued HENRY KIM
Green Building Final 7/12/2021 Approved HENRY KIM
HVAC-Final 7/12/2021 Corrections Issued HENRY KIM
PLUMBING-Final 7/12/2021 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Not Ready HENRY KIM
Smoke Detectors 7/12/2021 Approved HENRY KIM
Gas Test 10/29/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Approved STEVEN BACK
ELECTRICAL-Final 11/24/2021 Approved STEVEN BACK
Final 11/24/2021 OK to Issue CofO STEVEN BACK
HVAC-Final 11/24/2021 Approved STEVEN BACK
PLUMBING-Final 11/24/2021 Approved STEVEN BACK