2210 W TEMPLE ST 90026
Certificate Information: 2210 W TEMPLE ST 90026
- Application / Permit
- 20016-20000-06305
- Plan Check / Job No.
- B20VN03787
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- <URM BLDG> CHANGE OF USE FROM REPAIR GARAGE TO (N) OFFICE
- Permit Issued
- Issued on 10/20/2020
- Issuing Office
- Current Status
- Permit Finaled on 6/2/2022
Permit Application Status History
| Submitted | 3/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | MARVEL DELACRUZ |
| Corrections Issued | 3/22/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 3/24/2020 | STEVEN KIM |
| Disabled Access Plans Picked Up | 3/24/2020 | APPLICANT |
| Building Plans Picked Up | 3/26/2020 | APPLICANT |
| Applicant returned to address corrections | 5/13/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 6/12/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 7/20/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 7/28/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 7/30/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/19/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/21/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 9/30/2020 | MARVEL DELACRUZ |
| Issued | 10/20/2020 | APPLICANT |
| Permit Finaled | 6/2/2022 | TIMOTHY BUXTON |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/16/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2020 | CECILIO NAVARRO |
| DAS Clearance | Cleared | 10/1/2020 | NORLITO MEDRANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/25/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 12/16/2020 | Partial Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 12/21/2020 | No Access for Inspection | KATY RAMIREZ |
| Footing/Foundation/Slab | 1/14/2021 | Partial Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 1/19/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Footing/Foundation/Slab | 1/26/2021 | Corrections Issued | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 1/28/2021 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 4/1/2021 | Corrections Issued | KATY RAMIREZ |
| Insulation | 4/8/2021 | Partial Inspection | KATY RAMIREZ |
| Light Gage Steel Frame | 4/8/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Drywall Nailing | 4/20/2021 | Corrections Issued | KATY RAMIREZ |
| Drywall Nailing | 4/21/2021 | No Access for Inspection | KATY RAMIREZ |
| Drywall Nailing | 4/28/2021 | No Access for Inspection | KATY RAMIREZ |
| Final | 5/27/2022 | Conditional Approval | TIMOTHY BUXTON |
| Grading Pre-Inspection | 5/27/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Final | 5/27/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 5/27/2022 | Approved | TIMOTHY BUXTON |
| Posting Pre-Inspection | 5/27/2022 | Approved | TIMOTHY BUXTON |
| Reinforced Masonry Frame | 5/27/2022 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 5/27/2022 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 5/27/2022 | Conditional Approval | TIMOTHY BUXTON |
| Final | 6/2/2022 | Permit Finaled | TIMOTHY BUXTON |
| Smoke Detectors | 6/2/2022 | Approved | TIMOTHY BUXTON |