2210 W TEMPLE ST 90026

Certificate Information: 2210 W TEMPLE ST 90026

Application / Permit
20016-20000-06305
Plan Check / Job No.
B20VN03787
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
<URM BLDG> CHANGE OF USE FROM REPAIR GARAGE TO (N) OFFICE
Permit Issued
Issued on 10/20/2020
Issuing Office
Current Status
Permit Finaled on 6/2/2022

Permit Application Status History

Submitted 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 MARVEL DELACRUZ
Corrections Issued 3/22/2020 MARVEL DELACRUZ
Quality Review Completed 3/24/2020 STEVEN KIM
Disabled Access Plans Picked Up 3/24/2020 APPLICANT
Building Plans Picked Up 3/26/2020 APPLICANT
Applicant returned to address corrections 5/13/2020 MARVEL DELACRUZ
Applicant returned to address corrections 6/12/2020 MARVEL DELACRUZ
Applicant returned to address corrections 7/20/2020 MARVEL DELACRUZ
Applicant returned to address corrections 7/28/2020 MARVEL DELACRUZ
Applicant returned to address corrections 7/30/2020 MARVEL DELACRUZ
Applicant returned to address corrections 8/19/2020 MARVEL DELACRUZ
Applicant returned to address corrections 8/21/2020 MARVEL DELACRUZ
Plan Check Approved 9/30/2020 MARVEL DELACRUZ
Issued 10/20/2020 APPLICANT
Permit Finaled 6/2/2022 TIMOTHY BUXTON

Permit Application Clearance Information

Sewer availability Cleared 4/16/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 4/17/2020 CECILIO NAVARRO
DAS Clearance Cleared 10/1/2020 NORLITO MEDRANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/25/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 12/16/2020 Partial Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 12/21/2020 No Access for Inspection KATY RAMIREZ
Footing/Foundation/Slab 1/14/2021 Partial Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 1/19/2021 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 1/26/2021 Corrections Issued KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 1/28/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 4/1/2021 Corrections Issued KATY RAMIREZ
Insulation 4/8/2021 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 4/8/2021 Not Ready for Inspection KATY RAMIREZ
Drywall Nailing 4/20/2021 Corrections Issued KATY RAMIREZ
Drywall Nailing 4/21/2021 No Access for Inspection KATY RAMIREZ
Drywall Nailing 4/28/2021 No Access for Inspection KATY RAMIREZ
Final 5/27/2022 Conditional Approval TIMOTHY BUXTON
Grading Pre-Inspection 5/27/2022 Approved TIMOTHY BUXTON
METHANE-Final 5/27/2022 Approved TIMOTHY BUXTON
METHANE-Rough 5/27/2022 Approved TIMOTHY BUXTON
Posting Pre-Inspection 5/27/2022 Approved TIMOTHY BUXTON
Reinforced Masonry Frame 5/27/2022 Approved TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 5/27/2022 SGSOV Approved TIMOTHY BUXTON
Smoke Detectors 5/27/2022 Conditional Approval TIMOTHY BUXTON
Final 6/2/2022 Permit Finaled TIMOTHY BUXTON
Smoke Detectors 6/2/2022 Approved TIMOTHY BUXTON