20752-20754 W COLLINS ST 91367
Certificate Information: 20752-20754 W COLLINS ST 91367
- Application / Permit
- 20016-20000-06245
- Plan Check / Job No.
- B20VN03731
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE 8'-4" X 5'-7" PORCH TO EXPAND FOYER AND CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 3/31/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2020 | ALDOUS CHIC |
| Corrections Issued | 3/3/2020 | ALDOUS CHIC |
| Plan Check Approved | 3/12/2020 | ROSENDO MEDINA |
| Issued | 3/31/2020 | LADBS |
| CofO in Progress | 6/12/2020 | HENRY KIM |
| CofO Issued | 6/19/2020 | JOHN JANSON |
| Permit Finaled | 6/19/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 3/3/2020 | BARTON HOLMES |
| Miscellaneous | Cleared | 3/3/2020 | STEVEN WECHSLER |
| Sewer availability | Cleared | 3/3/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | A R Y Construction & Marketing Inc; Lic. No.: 953632-B | 5776 - D LINDERO CANYON ROAD # 376 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/17/2020 | Conditional Approval | HENRY KIM |
| BUILDING-Rough-Frame | 4/21/2020 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Rough | 4/21/2020 | Not Ready for Inspection | HENRY KIM |
| Footing/Foundation/Slab | 4/21/2020 | Approved | HENRY KIM |
| Green Building Rough | 4/21/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 4/21/2020 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 5/6/2020 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Rough | 5/6/2020 | Corrections Issued | HENRY KIM |
| Green Building Rough | 5/6/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 5/6/2020 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 5/11/2020 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 5/11/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2020 | Partial Approval | HENRY KIM |
| Green Building Rough | 5/11/2020 | Not Ready for Inspection | HENRY KIM |
| HVAC-Rough | 5/11/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 5/11/2020 | Approved | HENRY KIM |
| Pre-Inspection | 5/11/2020 | Corrections Issued | HENRY KIM |
| Sewer | 5/11/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 5/15/2020 | Partial Approval | HENRY KIM |
| Green Building Rough | 5/15/2020 | Approved | HENRY KIM |
| Insulation | 5/15/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 5/15/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 5/26/2020 | Approved | HENRY KIM |
| Drywall Nailing | 5/26/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 5/26/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 6/8/2020 | Corrections Issued | HENRY KIM |
| Final | 6/8/2020 | Corrections Issued | HENRY KIM |
| Green Building Final | 6/8/2020 | Approved | HENRY KIM |
| HVAC-Final | 6/8/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 6/8/2020 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 6/8/2020 | SGSOV Not Ready | HENRY KIM |
| Smoke Detectors | 6/8/2020 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 6/10/2020 | SGSOV Not Ready | HENRY KIM |
| ELECTRICAL-Final | 6/12/2020 | Approved | HENRY KIM |
| Final | 6/12/2020 | OK to Issue CofO | HENRY KIM |
| HVAC-Final | 6/12/2020 | Approved | HENRY KIM |
| PLUMBING-Final | 6/12/2020 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 6/12/2020 | SGSOV Approved | HENRY KIM |