19960-19962 W STRATHERN ST 91306
Certificate Information: 19960-19962 W STRATHERN ST 91306
- Application / Permit
- 20016-20000-06233
- Plan Check / Job No.
- B20VN03730
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 21'-0" X 34'-6" ATTACHED 3-CAR GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WOOD FRAME PRESCRIPTIVE PROVISION.
- Permit Issued
- Issued on 7/2/2020
- Issuing Office
- Current Status
- CofO Issued on 2/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2020 | JENNIFER LEE |
| Corrections Issued | 3/9/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 4/29/2020 | SERGIO MUNIZ |
| Applicant returned to address corrections | 5/12/2020 | JENNIFER LEE |
| Plan Check Approved | 5/20/2020 | GURUNATH NESARAJAH |
| Issued | 7/2/2020 | APPLICANT |
| CofO in Progress | 1/28/2021 | HENRY KIM |
| CofO Issued | 2/4/2021 | JOHN JANSON |
| Permit Finaled | 2/4/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/31/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/31/2020 | JOHN TRIANTAFYLLOS |
| CPC | Cleared | 4/6/2020 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/30/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 7/30/2020 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 8/5/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 8/5/2020 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 8/7/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 8/21/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 8/21/2020 | Corrections Issued | HENRY KIM |
| Green Building Rough | 8/21/2020 | Not Ready for Inspection | HENRY KIM |
| HVAC-Rough | 8/21/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 8/21/2020 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 8/27/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 8/27/2020 | Corrections Issued | HENRY KIM |
| Green Building Rough | 8/27/2020 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 9/29/2020 | Not Ready for Inspection | HENRY KIM |
| Green Building Rough | 9/29/2020 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Rough | 10/29/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2020 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 10/29/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 10/29/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2020 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 11/10/2020 | Approved | HENRY KIM |
| Drywall Nailing | 11/10/2020 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2020 | Approved | HENRY KIM |
| Insulation | 11/10/2020 | Approved | HENRY KIM |
| Drywall Nailing | 11/24/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 11/24/2020 | Approved | HENRY KIM |
| Green Building Rough | 11/24/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 11/24/2020 | Approved | HENRY KIM |
| Drywall Nailing | 11/30/2020 | Approved | HENRY KIM |
| Shower Pan | 11/30/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 12/23/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| Final | 12/23/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| Green Building Final | 12/23/2020 | Not Ready for Inspection | JOSEPH SAGEN |
| Smoke Detectors | 12/23/2020 | Corrections Issued | JOSEPH SAGEN |
| ELECTRICAL-Final | 12/30/2020 | Corrections Issued | HENRY KIM |
| Final | 12/30/2020 | Not Ready for Inspection | HENRY KIM |
| Green Building Final | 12/30/2020 | Approved | HENRY KIM |
| HVAC-Final | 12/30/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 12/30/2020 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 12/30/2020 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 12/30/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 1/13/2021 | Approved | HENRY KIM |
| Final | 1/13/2021 | Corrections Issued | HENRY KIM |
| Gas Test | 1/13/2021 | Approved | HENRY KIM |
| HVAC-Final | 1/13/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 1/13/2021 | Corrections Issued | HENRY KIM |
| Final | 1/28/2021 | OK to Issue CofO | HENRY KIM |
| HVAC-Final | 1/28/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 1/28/2021 | Approved | HENRY KIM |