17638 W HAMLIN ST 91406

Certificate Information: 17638 W HAMLIN ST 91406

Application / Permit
20016-20000-06185
Plan Check / Job No.
B20VN03689
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 5/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2020 APPLICANT
Assigned to Plan Check Engineer 3/3/2020 JEROME MAGAT PALMA
Corrections Issued 3/3/2020 JEROME MAGAT PALMA
Building Plans Picked Up 3/6/2020 APPLICANT
Plan Check Approved 4/7/2020 JEROME MAGAT PALMA
Issued 5/5/2020 LADBS
CofO in Progress 12/15/2020 STEVEN BACK
CofO in Progress 12/15/2020 STEVEN BACK
CofO Issued 12/17/2020 DONALD SUNSERI
Permit Finaled 12/17/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 3/13/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/13/2020 LEE GUILBEAUX
Sewer availability Cleared 3/13/2020 LEE GUILBEAUX
ZI Cleared 3/13/2020 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/27/2020 Approved STEVEN BACK
Sewer 5/27/2020 Partial Approval STEVEN BACK
Sewer 6/10/2020 Approved STEVEN BACK
Underground Mechanical 6/10/2020 Partial Approval STEVEN BACK
Pre-Inspection 6/22/2020 Approved STEVEN BACK
Footing/Foundation/Slab 7/17/2020 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 7/24/2020 Approved STEVEN BACK
Footing/Foundation/Slab 7/24/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 9/1/2020 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 9/1/2020 Approved STEVEN BACK
HVAC-Rough 9/1/2020 Corrections Issued STEVEN BACK
PLUMBING-Rough 9/1/2020 Corrections Issued STEVEN BACK
HVAC-Rough 9/9/2020 Approved STEVEN BACK
PLUMBING-Rough 9/9/2020 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 9/15/2020 Corrections Issued STEVEN BACK
Insulation 9/15/2020 Partial Approval STEVEN BACK
PLUMBING-Rough 9/15/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 9/23/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/23/2020 Approved STEVEN BACK
Green Building Rough 9/23/2020 Approved STEVEN BACK
Insulation 9/23/2020 Approved STEVEN BACK
Drywall Nailing 9/29/2020 Approved STEVEN BACK
Shower Pan 10/7/2020 Approved STEVEN BACK
Interior/Exterior Lathing 10/15/2020 Approved STEVEN BACK
Final 11/25/2020 Corrections Issued STEVEN BACK
Green Building Final 11/25/2020 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 11/25/2020 SGSOV Approved STEVEN BACK
Smoke Detectors 11/25/2020 Approved STEVEN BACK
ELECTRICAL-Final 12/15/2020 Approved STEVEN BACK
Final 12/15/2020 OK to Issue CofO STEVEN BACK
HVAC-Final 12/15/2020 Approved STEVEN BACK