13938 W AZTEC ST 91342
Certificate Information: 13938 W AZTEC ST 91342
- Application / Permit
- 20016-20000-06169
- Plan Check / Job No.
- B20VN03680
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 12'-2" X 18'-2" DETACHED 1-CAR GARAGE TO (N) ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 8/18/2021
- Issuing Office
- Current Status
- CofO Issued on 1/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2020 | JENNIFER LEE |
| Corrections Issued | 3/6/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 5/15/2020 | ROSENDO MEDINA |
| Plan Check Approved | 7/8/2020 | JEROME MAGAT PALMA |
| Issued | 8/18/2021 | APPLICANT |
| CofO in Progress | 1/10/2023 | JOHN COLEMAN |
| Permit Finaled | 1/25/2023 | MICHAEL SMITH |
| CofO Issued | 1/25/2023 | MICHAEL SMITH |
| Permit Finaled | 1/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/6/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Architect | Buangsuwon,, Panupong; Lic. No.: C18986 | 720 ALAMEDA ST ALTADENA, CA 91001 |
| Contractor | Y'Hoyada Construction; Lic. No.: 1026529-B | 3916 MAGNOLIA AVENUE LYNWOOD, CA 90262 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/14/2021 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 9/28/2021 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 10/14/2021 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Underground Mechanical | 10/15/2021 | Partial Approval | JOHN HAYES |
| Sewer | 10/21/2021 | Approved | JOHN HAYES |
| Underground Mechanical | 10/21/2021 | Approved | JOHN HAYES |
| Deputy Drilled-In Anchors | 11/1/2021 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 11/1/2021 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 11/4/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 11/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 11/30/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/4/2022 | Corrections Issued | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 1/4/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/10/2022 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 2/10/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/23/2022 | Approved | JOHN HAYES |
| Green Building Rough | 2/23/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 2/23/2022 | Approved | JOHN HAYES |
| Insulation | 3/16/2022 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 3/29/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 4/6/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2022 | Approved | JOHN HAYES |
| Green Building Rough | 4/6/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 4/13/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 4/13/2022 | Approved | JOHN HAYES |
| Final | 12/8/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 12/8/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 12/8/2022 | Approved | ARAM AVEDISIAN |
| Final | 1/9/2023 | Conditional Approval | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 1/9/2023 | SGSOV Approved | JOHN COLEMAN |