3583 1/2 N VERDUGO ROAD 90065

Certificate Information: 3583 1/2 N VERDUGO ROAD 90065

Application / Permit
20016-20000-05999
Plan Check / Job No.
B20VN03585
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'8"X12'6-1/2" DET. GARAGE TO ADU WITH 13'4"X4'7" ADDITION PER LAMC 12.22A.33(c) and (d)
Permit Issued
Issued on 12/8/2020
Issuing Office
Current Status
CofO Issued on 2/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2020 APPLICANT
Green Plans Picked Up 3/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 MARVEL DELACRUZ
Corrections Issued 3/22/2020 MARVEL DELACRUZ
Quality Review Completed 3/24/2020 STEVEN KIM
Building Plans Picked Up 3/26/2020 APPLICANT
Applicant returned to address corrections 6/18/2020 MARVEL DELACRUZ
Applicant returned to address corrections 9/18/2020 MARVEL DELACRUZ
Applicant returned to address corrections 11/9/2020 MARVEL DELACRUZ
Applicant returned to address corrections 11/25/2020 MARVEL DELACRUZ
Plan Check Approved 12/7/2020 MARVEL DELACRUZ
Issued 12/8/2020 APPLICANT
CofO in Progress 8/24/2021 BRIAN SULLIVAN
Permit Finaled 2/12/2023 DANIEL ORRANTE
CofO Issued 2/12/2023 DANIEL ORRANTE
Permit Finaled 2/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/29/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 6/29/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/30/2020 CECILIO NAVARRO
Sewer availability Cleared 6/30/2020 CECILIO NAVARRO
ZA Case Cleared 6/30/2020 SARAHI ORTEGA
ZI Cleared 6/30/2020 SARAHI ORTEGA
Grading Pre-Inspection Cleared 7/27/2020 PATRICK MISCHLICH
Green Code Cleared 8/17/2020 DAVID MATSON
Construction near power lines Cleared 8/31/2020 RIDWAN HARDY
Construction within easement Cleared 8/31/2020 RIDWAN HARDY
ZI Cleared 9/9/2020 ADRINEH MELKONIAN

Contact Information

Architect Miller,, Jeffrey A; Lic. No.: C37366 448B ROSECRANS AVENUE      MANHATTAN BEACH, CA 90266
Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/11/2020 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/5/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 2/22/2021 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 3/10/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/11/2021 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/30/2021 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/30/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/30/2021 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 3/30/2021 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 3/30/2021 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 3/30/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 3/30/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 4/8/2021 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 4/8/2021 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 4/8/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 4/8/2021 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/15/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/15/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 4/15/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 4/15/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 4/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 5/4/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 5/4/2021 Corrections Issued HAMIK HARTOUNIAN
Insulation 5/7/2021 Approved HAMIK HARTOUNIAN
Wood Frame 5/7/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 5/10/2021 Corrections Issued THOMAS LOGRASSO
Green Building Rough 5/10/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/10/2021 Approved THOMAS LOGRASSO
Shower Pan 5/10/2021 Approved THOMAS LOGRASSO
Drywall Nailing 5/19/2021 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 6/2/2021 Approved HAMIK HARTOUNIAN
Gas Test 6/2/2021 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/24/2021 Approved HAMIK HARTOUNIAN
Final 6/24/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 6/24/2021 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 6/24/2021 Approved HAMIK HARTOUNIAN
MERV13>=Rough 6/24/2021 Approved HAMIK HARTOUNIAN
Pre-Inspection 6/24/2021 Partial Inspection ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 6/24/2021 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 6/24/2021 Approved HAMIK HARTOUNIAN
Final 8/18/2021 Corrections Issued BRIAN SULLIVAN
Green Building Final 8/18/2021 Not Ready for Inspection BRIAN SULLIVAN
Final 8/23/2021 OK to Issue CofO BRIAN SULLIVAN
Green Building Final 8/23/2021 Approved BRIAN SULLIVAN