10253 N KEWEN AVE 91331

Certificate Information: 10253 N KEWEN AVE 91331

Application / Permit
20016-20000-05951
Plan Check / Job No.
B20VN03560
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 22' X 21' ACCESSORY DWELLING UNIT PER STATE ORDINANCE 186,481.
Permit Issued
Issued on 7/14/2021
Issuing Office
Current Status
CofO Issued on 3/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2020 APPLICANT
Assigned to Plan Check Engineer 2/28/2020 ALDOUS CHIC
Corrections Issued 2/28/2020 ALDOUS CHIC
Applicant returned to address corrections 3/9/2021 SERGIO MUNIZ
Applicant returned to address corrections 6/18/2021 SERGIO MUNIZ
Applicant returned to address corrections 7/6/2021 SERGIO MUNIZ
Plan Check Approved 7/14/2021 SERGIO MUNIZ
Issued 7/14/2021 APPLICANT
Building Plans Picked Up 7/16/2021 APPLICANT
CofO in Progress 1/27/2022 MICHEL ABAJAN
Permit Finaled 3/17/2022 JOHN JANSON
CofO Issued 3/17/2022 JOHN JANSON
Permit Finaled 3/17/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/22/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/22/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 12/22/2020 GUILLERMO PETRA
Sewer availability Cleared 12/22/2020 GUILLERMO PETRA
Clean Up Green Up Cleared 3/18/2021 MIGUEL GAMBOA
Hydrant and Access approval Cleared 5/2/2021 JOHN CONNEALLY
Construction near power lines Cleared 6/12/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205
Engineer Kaligi,, Sean; Lic. No.: M37797 655 N CENTRAL AVE 17TH FL      GLENDALE, CA 91203

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2021 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 10/12/2021 Partial Inspection MICHEL ABAJAN
METHANE-Barrier 10/12/2021 Partial Inspection MICHEL ABAJAN
METHANE-Subgrade 10/12/2021 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 10/25/2021 Approved MICHEL ABAJAN
METHANE-Barrier 10/25/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 10/25/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/18/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 11/29/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/29/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 11/29/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/29/2021 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Partial Approval MARK JOHNSON
PLUMBING-Rough 12/2/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 12/7/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/7/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/7/2021 Partial Approval JENNIFER RABUCHIN
METHANE-Rough 12/7/2021 Approved JENNIFER RABUCHIN
Shower Pan 12/7/2021 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 12/7/2021 Approved JENNIFER RABUCHIN
Insulation 12/13/2021 Approved MICHEL ABAJAN
Drywall Nailing 12/16/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/16/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/27/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/27/2022 Approved MICHEL ABAJAN
Final 1/27/2022 OK to Issue CofO MICHEL ABAJAN
Green Building Final 1/27/2022 Approved MICHEL ABAJAN
Green Building Rough 1/27/2022 Approved MICHEL ABAJAN
HVAC-Final 1/27/2022 Approved MICHEL ABAJAN
PLUMBING-Final 1/27/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/27/2022 SGSOV Approved MICHEL ABAJAN
Service/Power Release 1/27/2022 Approved MICHEL ABAJAN
Smoke Detectors 1/27/2022 Approved MICHEL ABAJAN