7537-7539 N ROYER AVE 91307
Certificate Information: 7537-7539 N ROYER AVE 91307
- Application / Permit
- 20016-20000-05942
- Plan Check / Job No.
- B20VN03551
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE 22' x 18' ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 3/2/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/16/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2020 | MARVEL DELACRUZ |
| Corrections Issued | 2/28/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 2/28/2020 | ANGELICA MARTINEZ |
| Issued | 3/2/2020 | LADBS |
| CofO in Progress | 6/12/2020 | DAVID STEPANYAN |
| Permit Finaled | 6/16/2020 | JOHN JANSON |
| CofO Issued | 6/16/2020 | JOHN JANSON |
| Permit Finaled | 6/16/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/28/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/20/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 3/20/2020 | Partial Approval | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 3/25/2020 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 4/7/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 4/7/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 4/7/2020 | Approved | DAVID STEPANYAN |
| Insulation | 4/9/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 4/9/2020 | Partial Approval | DAVID STEPANYAN |
| Shower Pan | 4/9/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 4/10/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 4/13/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 4/14/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 4/15/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 5/13/2020 | Corrections Issued | DAVID STEPANYAN |
| Final | 6/12/2020 | OK to Issue CofO | DAVID STEPANYAN |
| Green Building Final | 6/12/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2020 | SGSOV Approved | DAVID STEPANYAN |
| Smoke Detectors | 6/12/2020 | Approved | DAVID STEPANYAN |