6022-6024 N VANTAGE AVE 91606
Certificate Information: 6022-6024 N VANTAGE AVE 91606
- Application / Permit
- 20016-20000-05923
- Plan Check / Job No.
- B20VN03533
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 25' 4" X 24' 1ST FLOOR IRR.-SHAPE PORTION OF (E) SINGLE FAMILY DWELLING TO JUNIOR ADU. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 5/28/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 2/28/2020 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 3/2/2020 | APPLICANT |
| Plan Check Approved | 3/11/2020 | GURUNATH NESARAJAH |
| Issued | 5/28/2020 | LADBS |
| CofO in Progress | 2/2/2024 | JOSE AVILA |
| Permit Finaled | 3/15/2024 | RUBEN SALAS |
| CofO Issued | 3/15/2024 | RUBEN SALAS |
| Permit Finaled | 3/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/2/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | 984 BROADWAY #302 CHULA VISTA, CA 91911 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/29/2020 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/6/2022 | Corrections Issued | RAFAEL CORTES |
| Final | 7/6/2022 | Not Ready for Inspection | RAFAEL CORTES |
| MERV13>=Final | 7/6/2022 | Not Ready for Inspection | RAFAEL CORTES |
| MERV13>=Rough | 7/6/2022 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 7/6/2022 | Corrections Issued | RAFAEL CORTES |
| ELECTRICAL-Final | 8/29/2022 | Approved | RAFAEL CORTES |
| HVAC-Final | 8/29/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Final | 8/29/2022 | Approved | RAFAEL CORTES |
| Underground Mechanical | 9/15/2022 | Not Ready for Inspection | RAFAEL CORTES |
| BUILDING-Rough-Frame | 7/18/2023 | Corrections Issued | JUAN VALENZUELA |
| Final | 7/18/2023 | Corrections Issued | JUAN VALENZUELA |
| MERV13>=Final | 7/18/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 7/18/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 7/18/2023 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 1/19/2024 | Approved | JOSE AVILA |
| Final | 1/19/2024 | Corrections Issued | JOSE AVILA |
| MERV13>=Final | 1/19/2024 | Approved | JOSE AVILA |
| MERV13>=Rough | 1/19/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 1/24/2024 | Approved | JOSE AVILA |
| Gas Test | 1/24/2024 | Approved | JOSE AVILA |
| HVAC-Final | 1/24/2024 | Conditional Approval | JOSE AVILA |
| PLUMBING-Final | 1/24/2024 | Approved | JOSE AVILA |
| Final | 1/25/2024 | Not Ready for Inspection | JOSE AVILA |
| Final | 2/1/2024 | OK to Issue CofO | JOSE AVILA |