6952 N TAMPA AVE 91335

Certificate Information: 6952 N TAMPA AVE 91335

Application / Permit
20016-20000-05871
Plan Check / Job No.
B20VN03495
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 20' X 20' 2-CAR GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 7/13/2020
Issuing Office
Current Status
CofO Issued on 11/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 2/28/2020 GURUNATH NESARAJAH
Corrections Issued 2/28/2020 GURUNATH NESARAJAH
Building Plans Picked Up 3/10/2020 APPLICANT
Plan Check Approved 7/6/2020 GURUNATH NESARAJAH
Issued 7/13/2020 APPLICANT
CofO in Progress 11/17/2020 VINCENT HANLEY
Permit Finaled 11/17/2020 MICHAEL SMITH
CofO Issued 11/17/2020 MICHAEL SMITH
Permit Finaled 11/17/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/1/2020 GABRIEL ROBLES
Sewer availability Cleared 4/1/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 4/8/2020 GUILLERMO PETRA
ZI Cleared 5/27/2020 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/31/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 7/31/2020 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 7/31/2020 Approved VINCENT HANLEY
PLUMBING-Rough 7/31/2020 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 8/20/2020 Not Ready for Inspection DAVID SCANTLIN
Gas Test 8/20/2020 Approved DAVID SCANTLIN
PLUMBING-Rough 8/20/2020 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 8/25/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 8/25/2020 Approved VINCENT HANLEY
Green Building Rough 8/25/2020 Approved VINCENT HANLEY
PLUMBING-Rough 8/25/2020 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 8/25/2020 Approved VINCENT HANLEY
Underground Mechanical 8/25/2020 Approved VINCENT HANLEY
Insulation 8/27/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/27/2020 Partial Approval VINCENT HANLEY
Shower Pan 8/27/2020 Approved VINCENT HANLEY
Drywall Nailing 9/2/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/2/2020 Approved VINCENT HANLEY
Final 11/2/2020 Corrections Issued VINCENT HANLEY
Green Building Final 11/2/2020 Approved VINCENT HANLEY
PLUMBING-Final 11/2/2020 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/2/2020 SGSOV Approved VINCENT HANLEY
Smoke Detectors 11/2/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 11/6/2020 Approved VINCENT HANLEY
Final 11/6/2020 Corrections Issued VINCENT HANLEY
HVAC-Final 11/6/2020 Approved VINCENT HANLEY
PLUMBING-Final 11/6/2020 Approved VINCENT HANLEY
Final 11/17/2020 OK to Issue CofO VINCENT HANLEY