12135 W HESBY ST 91607

Certificate Information: 12135 W HESBY ST 91607

Application / Permit
20016-20000-05846
Plan Check / Job No.
B20VN03469
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 5/27/2020
Issuing Office
Current Status
CofO Issued on 5/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 ROSENDO MEDINA
Corrections Issued 3/21/2020 ROSENDO MEDINA
Quality Review Completed 3/23/2020 CHON CHIO KUO
Building Plans Picked Up 3/26/2020 APPLICANT
Green Plans Picked Up 3/26/2020 APPLICANT
Plan Check Approved 5/27/2020 ROSENDO MEDINA
Issued 5/27/2020 APPLICANT
CofO in Progress 1/28/2021 ARAM AVEDISIAN
CofO Issued 5/1/2021 MICHAEL SMITH
Permit Finaled 5/1/2021 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 4/15/2020 WALTER RAMIREZ
Construction within easement Cleared 4/15/2020 WALTER RAMIREZ
Specific Plan Cleared 4/20/2020 OLGA AYALA
Hydrant and Access approval Cleared 5/1/2020 GEORGE SUCHAND
Address approval Cleared 5/5/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/5/2020 ADRIAN CASTRO
Sewer availability Cleared 5/5/2020 ADRIAN CASTRO
Green Code Cleared 5/12/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/1/2020 Approved BRENDAN LOONEY
PLUMBING-Rough 8/27/2020 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 9/2/2020 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 9/2/2020 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 9/15/2020 Not Ready for Inspection BRENDAN LOONEY
Shower Pan 9/15/2020 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 9/15/2020 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 9/21/2020 Partial Approval DANIEL ORRANTE
Wood Frame 9/25/2020 Approved BRENDAN LOONEY
Insulation 9/29/2020 Approved BRENDAN LOONEY
Interior/Exterior Lathing 9/29/2020 Partial Approval BRENDAN LOONEY
Drywall Nailing 10/13/2020 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 12/18/2020 Approved BRENDAN LOONEY
Final 12/18/2020 Corrections Issued BRENDAN LOONEY
Green Building Final 12/18/2020 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 12/18/2020 Approved BRENDAN LOONEY
HVAC-Final 12/18/2020 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 12/18/2020 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 12/18/2020 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 12/18/2020 Approved BRENDAN LOONEY
Final 1/20/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Final 1/20/2021 Approved BRENDAN LOONEY
Final 1/28/2021 OK to Issue CofO ARAM AVEDISIAN