22521 W SATICOY ST 91307
Certificate Information: 22521 W SATICOY ST 91307
- Application / Permit
- 20016-20000-05816
- Plan Check / Job No.
- B20VN03429
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 2/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | ALDOUS CHIC |
| Corrections Issued | 2/27/2020 | ALDOUS CHIC |
| Plan Check Approved | 2/27/2020 | HAYATO TSUCHIYA |
| Issued | 2/27/2020 | LADBS |
| CofO in Progress | 12/16/2020 | DAVID STEPANYAN |
| CofO Issued | 12/17/2020 | JOHN JANSON |
| Permit Finaled | 12/17/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/27/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/27/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/4/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 5/4/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 5/4/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 6/10/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 6/10/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 6/10/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 7/17/2020 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 7/17/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 7/17/2020 | Partial Approval | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 7/27/2020 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 7/27/2020 | Partial Approval | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 8/5/2020 | Approved | DAVID STEPANYAN |
| Footing/Foundation/Slab | 8/5/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 8/17/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 8/17/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 8/17/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 9/24/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 9/24/2020 | Approved | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 9/24/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 9/24/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/1/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 10/1/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 10/1/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 10/1/2020 | Partial Approval | DAVID STEPANYAN |
| Insulation | 10/7/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 10/16/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 10/16/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 11/20/2020 | Corrections Issued | DAVID STEPANYAN |
| Final | 11/20/2020 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Final | 11/20/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 11/20/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 11/20/2020 | SGSOV Approved | DAVID STEPANYAN |
| Smoke Detectors | 11/20/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 12/7/2020 | Approved | DAVID STEPANYAN |
| Final | 12/7/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Gas Test | 12/7/2020 | Approved | DAVID STEPANYAN |
| Service/Power Release | 12/7/2020 | Approved | DAVID STEPANYAN |
| Final | 12/15/2020 | OK to Issue CofO | DAVID STEPANYAN |