22521 W SATICOY ST 91307

Certificate Information: 22521 W SATICOY ST 91307

Application / Permit
20016-20000-05816
Plan Check / Job No.
B20VN03429
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 2/27/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 ALDOUS CHIC
Corrections Issued 2/27/2020 ALDOUS CHIC
Plan Check Approved 2/27/2020 HAYATO TSUCHIYA
Issued 2/27/2020 LADBS
CofO in Progress 12/16/2020 DAVID STEPANYAN
CofO Issued 12/17/2020 JOHN JANSON
Permit Finaled 12/17/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/27/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/27/2020 ADRIAN CASTRO
Sewer availability Cleared 2/27/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/4/2020 Not Ready for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 5/4/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 5/4/2020 Not Ready for Inspection DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 6/10/2020 Not Ready for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 6/10/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 6/10/2020 Not Ready for Inspection DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 7/17/2020 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 7/17/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 7/17/2020 Partial Approval DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 7/27/2020 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 7/27/2020 Partial Approval DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 8/5/2020 Approved DAVID STEPANYAN
Footing/Foundation/Slab 8/5/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 8/17/2020 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 8/17/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 8/17/2020 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 9/24/2020 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 9/24/2020 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 9/24/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 9/24/2020 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 9/24/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 10/1/2020 Approved DAVID STEPANYAN
Green Building Rough 10/1/2020 Approved DAVID STEPANYAN
HVAC-Rough 10/1/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 10/1/2020 Partial Approval DAVID STEPANYAN
Insulation 10/7/2020 Approved DAVID STEPANYAN
Drywall Nailing 10/16/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 10/16/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 11/20/2020 Corrections Issued DAVID STEPANYAN
Final 11/20/2020 Corrections Issued DAVID STEPANYAN
HVAC-Final 11/20/2020 Approved DAVID STEPANYAN
PLUMBING-Final 11/20/2020 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/20/2020 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 11/20/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 12/7/2020 Approved DAVID STEPANYAN
Final 12/7/2020 Not Ready for Inspection DAVID STEPANYAN
Gas Test 12/7/2020 Approved DAVID STEPANYAN
Service/Power Release 12/7/2020 Approved DAVID STEPANYAN
Final 12/15/2020 OK to Issue CofO DAVID STEPANYAN