1322 W ARABIC ST 90744
Certificate Information: 1322 W ARABIC ST 90744
- Application / Permit
- 20016-20000-05626
- Plan Check / Job No.
- B20VN03288
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-1" X 20'-2" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2020 | JENNIFER LEE |
| Corrections Issued | 2/27/2020 | JENNIFER LEE |
| Building Plans Picked Up | 2/28/2020 | APPLICANT |
| Plan Check Approved | 3/5/2020 | JENNIFER LEE |
| Issued | 3/5/2020 | LADBS |
| CofO in Progress | 2/19/2021 | JOHN KLARIN |
| Permit Finaled | 7/8/2021 | DEROLD HAUFF |
| CofO Issued | 7/8/2021 | DEROLD HAUFF |
| Permit Finaled | 7/8/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/28/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/8/2020 | Partial Inspection | JOHN KLARIN |
| PLUMBING-Rough | 10/8/2020 | Partial Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/19/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 10/19/2020 | Approved | JOHN KLARIN |
| Green Building Rough | 10/19/2020 | Approved | JOHN KLARIN |
| MERV13>=Rough | 10/19/2020 | Approved | JOHN KLARIN |
| METHANE-Rough | 10/19/2020 | Approved | JOHN KLARIN |
| Insulation | 10/23/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 10/23/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 10/27/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 12/1/2020 | Approved | JOHN KLARIN |
| Final | 12/1/2020 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 12/1/2020 | Corrections Issued | JOHN KLARIN |
| MERV13>=Final | 12/1/2020 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2020 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 12/1/2020 | No Access for Inspection | JOHN KLARIN |
| Smoke Detectors | 12/1/2020 | Approved | JOHN KLARIN |
| Final | 2/18/2021 | OK to Issue CofO | JOHN KLARIN |
| Green Building Final | 2/18/2021 | Approved | JOHN KLARIN |