1322 W ARABIC ST 90744

Certificate Information: 1322 W ARABIC ST 90744

Application / Permit
20016-20000-05626
Plan Check / Job No.
B20VN03288
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'-1" X 20'-2" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 3/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2020 APPLICANT
Assigned to Plan Check Engineer 2/25/2020 JENNIFER LEE
Corrections Issued 2/27/2020 JENNIFER LEE
Building Plans Picked Up 2/28/2020 APPLICANT
Plan Check Approved 3/5/2020 JENNIFER LEE
Issued 3/5/2020 LADBS
CofO in Progress 2/19/2021 JOHN KLARIN
Permit Finaled 7/8/2021 DEROLD HAUFF
CofO Issued 7/8/2021 DEROLD HAUFF
Permit Finaled 7/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/28/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 2/28/2020 GUILLERMO PETRA
Sewer availability Cleared 2/28/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/8/2020 Partial Inspection JOHN KLARIN
PLUMBING-Rough 10/8/2020 Partial Inspection JOHN KLARIN
BUILDING-Rough-Frame 10/19/2020 Approved JOHN KLARIN
ELECTRICAL-Rough 10/19/2020 Approved JOHN KLARIN
Green Building Rough 10/19/2020 Approved JOHN KLARIN
MERV13>=Rough 10/19/2020 Approved JOHN KLARIN
METHANE-Rough 10/19/2020 Approved JOHN KLARIN
Insulation 10/23/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 10/23/2020 Approved JOHN KLARIN
Drywall Nailing 10/27/2020 Approved JOHN KLARIN
ELECTRICAL-Final 12/1/2020 Approved JOHN KLARIN
Final 12/1/2020 Corrections Issued JOHN KLARIN
Green Building Final 12/1/2020 Corrections Issued JOHN KLARIN
MERV13>=Final 12/1/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/1/2020 SGSOV Approved JOHN KLARIN
Service/Power Release 12/1/2020 No Access for Inspection JOHN KLARIN
Smoke Detectors 12/1/2020 Approved JOHN KLARIN
Final 2/18/2021 OK to Issue CofO JOHN KLARIN
Green Building Final 2/18/2021 Approved JOHN KLARIN