20900 W SHERMAN WAY 91303

Certificate Information: 20900 W SHERMAN WAY 91303

Application / Permit
20016-20000-05499
Plan Check / Job No.
B20VN03196
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
EXTERIOR ALTERATION, REPAIR 65'-10" X 75'-0" PORTION OF (E) DAMAGED ROOF & REINFORCE ROOF FRAMING FOR ROOF TOP UNITS.
Permit Issued
Issued on 5/22/2020
Issuing Office
Current Status
Permit Finaled on 12/23/2021

Permit Application Status History

Submitted 2/24/2020 APPLICANT
Disabled Access Plans Picked Up 3/6/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 ARTIN ZARUKIAN
Corrections Issued 3/14/2020 ARTIN ZARUKIAN
Quality Review Completed 3/16/2020 GUANG MIN TUNG
Building Plans Picked Up 3/17/2020 APPLICANT
Plan Check Approved 5/5/2020 ARTIN ZARUKIAN
Issued 5/22/2020 APPLICANT
Permit Finaled 12/22/2021 JEFFREY FULTON

Permit Application Clearance Information

"Q" conditions Cleared 4/22/2020 DOMINICK ORTIZ
ZI Cleared 4/22/2020 DOMINICK ORTIZ
DAS Clearance Cleared 4/30/2020 HAYATO TSUCHIYA

Contact Information

Engineer Kennedy,, Thomas James; Lic. No.: C74144 5105 E LOS ANGELES AVE 207      SIMI VALLEY, CA 93063

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 7/13/2020 Partial Inspection JEFFREY FULTON
Pre-Inspection 7/13/2020 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 8/4/2020 Approved HAMID PISHEHVAR
Footing/Foundation/Slab 8/6/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/7/2020 Approved HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 8/26/2020 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 9/1/2020 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 9/25/2020 Conditional Approval JEFFREY FULTON
Pre-Inspection 10/2/2020 Not Ready for Inspection JEFFREY FULTON
Wall Anchors 10/2/2020 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/2/2020 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 10/6/2020 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Approved JEFFREY FULTON
Wood Frame 11/20/2020 Partial Inspection JEFFREY FULTON
Insulation 11/30/2020 No Access for Inspection JEFFREY FULTON
Interior/Exterior Lathing 11/30/2020 No Access for Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 12/1/2020 Conditional Approval JEFFREY FULTON
Insulation 12/1/2020 Approved JEFFREY FULTON
Interior/Exterior Lathing 12/1/2020 Approved JEFFREY FULTON
Drywall Nailing 12/9/2020 Approved JEFFREY FULTON
Grading Pre-Inspection 1/19/2021 No Access for Inspection JEFFREY FULTON
T-Bar Ceiling 1/19/2021 No Access for Inspection JEFFREY FULTON
T-Bar Ceiling 1/25/2021 Partial Inspection JEFFREY FULTON
Wood Frame 1/25/2021 Approved JEFFREY FULTON
Final 2/5/2021 Corrections Issued JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 2/5/2021 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 2/5/2021 Not Ready for Inspection JEFFREY FULTON
Final 3/31/2021 Partial Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 3/31/2021 SGSOV Approved JEFFREY FULTON
Smoke Detectors 3/31/2021 Approved JEFFREY FULTON
Final 12/22/2021 Permit Finaled JEFFREY FULTON