9621 N LEV AVE 91331

Certificate Information: 9621 N LEV AVE 91331

Application / Permit
20016-20000-05397
Plan Check / Job No.
B20VN03130
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert the detached garage into an Accessory Dwelling Unit
Permit Issued
Issued on 2/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/5/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2020 APPLICANT
Assigned to Plan Check Engineer 2/24/2020 ANGELICA DAVE
Corrections Issued 2/24/2020 ANGELICA DAVE
Plan Check Approved 2/24/2020 HAYATO TSUCHIYA
Issued 2/24/2020 LADBS
CofO in Progress 10/23/2020 MICHEL ABAJAN
Permit Finaled 12/5/2020 MICHAEL SMITH
CofO Issued 12/5/2020 MICHAEL SMITH
Permit Finaled 12/5/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/24/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 2/24/2020 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 2/24/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/24/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/3/2020 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 4/6/2020 Approved MICHEL ABAJAN
Underground Mechanical 4/6/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 4/24/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/24/2020 Approved MICHEL ABAJAN
Green Building Rough 4/24/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 4/24/2020 Approved MICHEL ABAJAN
HVAC-Rough 5/8/2020 Approved MICHEL ABAJAN
Insulation 5/8/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/8/2020 Approved MICHEL ABAJAN
Drywall Nailing 6/10/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 8/6/2020 Approved MICHEL ABAJAN
Final 8/6/2020 Corrections Issued MICHEL ABAJAN
Green Building Final 8/6/2020 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 8/6/2020 Approved MICHEL ABAJAN
PLUMBING-Final 8/6/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/6/2020 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 8/6/2020 Approved MICHEL ABAJAN
Final 9/10/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 9/10/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/10/2020 SGSOV Approved MICHEL ABAJAN
Final 10/23/2020 OK to Issue CofO MICHEL ABAJAN