1203 1/2 E MAURETANIA ST 90744

Certificate Information: 1203 1/2 E MAURETANIA ST 90744

Application / Permit
20016-20000-05185
Plan Check / Job No.
B20VN03004
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED TO ACCESSORY DWELLING UNIT (360 SQ FT)
Permit Issued
Issued on 6/17/2020
Issuing Office
Current Status
CofO Issued on 8/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2020 APPLICANT
Assigned to Plan Check Engineer 2/24/2020 JEROME MAGAT PALMA
Corrections Issued 2/24/2020 JEROME MAGAT PALMA
Building Plans Picked Up 2/27/2020 APPLICANT
Plan Check Approved 6/17/2020 JEROME MAGAT PALMA
Issued 6/17/2020 APPLICANT
CofO in Progress 8/1/2025 EUGENE CASSIDY
CofO Issued 8/4/2025 ANSON MAGLASANG
Permit Finaled 8/4/2025 ANSON MAGLASANG

Permit Application Clearance Information

ZA Case Cleared 4/13/2020 MIGUEL GAMBOA
Address approval Cleared 4/30/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 4/30/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 6/4/2020 ERIK BEASLEY

Contact Information

Contractor Ochoa Victor Manuel; Lic. No.: 908306-B 13700 FOOTHILL BLVD #920151      SYLMAR, CA 91342

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/16/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 10/1/2020 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 10/1/2020 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 10/1/2020 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 10/1/2020 Not Ready for Inspection JOSEPH MCGARRY
METHANE-Rough 10/1/2020 Approved JOSEPH MCGARRY
PLUMBING-Rough 10/1/2020 Not Ready for Inspection JOSEPH MCGARRY
Wood Frame 10/1/2020 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 10/14/2020 Partial Approval JOHN KLARIN
Green Building Rough 10/14/2020 Approved JOHN KLARIN
Insulation 10/20/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 10/22/2020 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 10/22/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 10/26/2020 Not Ready for Inspection DAVID FEILER
Drywall Nailing 10/30/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 11/20/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 3/8/2021 Conditional Approval JOHN KLARIN
Final 3/8/2021 Corrections Issued JOHN KLARIN
Green Building Final 3/8/2021 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 3/8/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 3/8/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 6/3/2021 Not Ready for Inspection EUGENE CASSIDY
Final 6/3/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 6/3/2021 Not Ready for Inspection EUGENE CASSIDY
Final 10/17/2024 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 5/29/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 5/29/2025 Not Ready for Inspection EUGENE CASSIDY
Final 5/29/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 5/29/2025 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 5/29/2025 Approved EUGENE CASSIDY
PLUMBING-Final 5/29/2025 Approved EUGENE CASSIDY
Final 7/25/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 7/25/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/1/2025 Approved EUGENE CASSIDY
Final 8/1/2025 OK to Issue CofO EUGENE CASSIDY