14524-14526 W ERWIN ST 91411
Certificate Information: 14524-14526 W ERWIN ST 91411
- Application / Permit
- 20016-20000-05038
- Plan Check / Job No.
- B20VN02902
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- CHANGE OF USE FROM AUTO REPAIR TO RETAIL
- Permit Issued
- Issued on 5/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | RAPHAEL ROSAS |
| Corrections Issued | 3/16/2020 | RAPHAEL ROSAS |
| Quality Review Completed | 3/18/2020 | CHON CHIO KUO |
| Disabled Access Plans Picked Up | 3/19/2020 | APPLICANT |
| Building Plans Picked Up | 3/24/2020 | APPLICANT |
| Plan Check Approved | 5/13/2020 | RAPHAEL ROSAS |
| Issued | 5/27/2020 | LADBS |
| TCO Issued (Expire Date: 12-08-2021) | 6/11/2021 | JEFFREY DURAN |
| CofO in Progress | 7/6/2021 | ANDREW DORSO |
| Permit Finaled | 7/30/2021 | JEFFREY DURAN |
| CofO Issued | 7/30/2021 | JEFFREY DURAN |
| Permit Finaled | 7/30/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/1/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 4/1/2020 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/2/2020 | GABRIEL ROBLES |
| DAS Clearance | Cleared | 4/16/2020 | RAPHAEL ROSAS |
| "Q" conditions | Cleared | 4/30/2020 | MARIANNE KING |
| Supp. Use District POD/CDO/TDO | Cleared | 4/30/2020 | MARIANNE KING |
| ZI | Cleared | 4/30/2020 | MARIANNE KING |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 6/10/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 8/11/2020 | Approved | DANIEL VARNUM |
| Drywall Nailing | 8/19/2020 | Approved | ANDREW DORSO |
| T-Bar Ceiling | 9/29/2020 | Not Ready for Inspection | ANDREW DORSO |
| T-Bar Ceiling | 10/29/2020 | Approved | ROBERT DAVIS |
| Final | 6/3/2021 | Corrections Issued | ANDREW DORSO |
| Reinforced Masonry Frame | 6/3/2021 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 6/3/2021 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 6/3/2021 | Approved | ANDREW DORSO |
| T-Bar Ceiling | 6/3/2021 | Approved | ANDREW DORSO |
| Final | 6/11/2021 | OK to Issue CofO | ANDREW DORSO |