15147 W GILMORE ST 91411

Certificate Information: 15147 W GILMORE ST 91411

Application / Permit
20016-20000-04952
Plan Check / Job No.
B20VN02835
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 2/27/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2020 APPLICANT
Assigned to Plan Check Engineer 2/19/2020 JEROME MAGAT PALMA
Corrections Issued 2/19/2020 JEROME MAGAT PALMA
Building Plans Picked Up 2/24/2020 APPLICANT
Plan Check Approved 2/27/2020 JEROME MAGAT PALMA
Issued 2/27/2020 LADBS
CofO in Progress 12/23/2020 DAVID MATSON
CofO in Progress 12/24/2020 DAVID MATSON
CofO Issued 1/4/2021 MICHAEL SMITH
Permit Finaled 1/4/2021 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 2/24/2020 MIGUEL GAMBOA
Address approval Cleared 2/26/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/26/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/26/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/12/2020 No Access for Inspection WILLIAM KUEHN
Footing/Foundation/Slab 8/13/2020 Approved DANIEL DREW
Sewer 8/13/2020 Approved DANIEL DREW
ELECTRICAL-Rough 9/22/2020 Approved WILLIAM KUEHN
HVAC-Rough 9/22/2020 Approved WILLIAM KUEHN
PLUMBING-Rough 9/22/2020 Approved WILLIAM KUEHN
Sewer 9/22/2020 Approved WILLIAM KUEHN
Underground Mechanical 9/22/2020 Partial Inspection WILLIAM KUEHN
Insulation 9/29/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 9/29/2020 Partial Inspection WILLIAM KUEHN
Shower Pan 9/29/2020 Approved WILLIAM KUEHN
Drywall Nailing 10/20/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 10/20/2020 Approved BEAU COLLINS
BUILDING-Rough-Frame 12/16/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/16/2020 Corrections Issued MICHEL ABAJAN
Final 12/16/2020 Corrections Issued MICHEL ABAJAN
Gas Test 12/16/2020 Approved MICHEL ABAJAN
HVAC-Final 12/16/2020 Approved MICHEL ABAJAN
PLUMBING-Final 12/16/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/16/2020 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/16/2020 Approved MICHEL ABAJAN
Final 12/22/2020 OK to Issue CofO DAVID MATSON
Final 12/23/2020 OK to Issue CofO DAVID MATSON