4847 N LAUREL CANYON BLVD 91607

Certificate Information: 4847 N LAUREL CANYON BLVD 91607

Application / Permit
20016-20000-04824
Plan Check / Job No.
B20VN02747
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Beauty Shop or Parlor
Work Description
CHANGE OF USE FROM OFFICE TO HAIR SALON WITH INTERIOR T.I. PER DESIGN
Permit Issued
Issued on 3/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2020 APPLICANT
Assigned to Plan Check Engineer 2/18/2020 ALDOUS CHIC
Corrections Issued 2/19/2020 ALDOUS CHIC
Building Plans Picked Up 2/20/2020 APPLICANT
Plan Check Approved 3/12/2020 ALDOUS CHIC
No Progress 3/12/2020 ALDOUS CHIC
Plan Check Approved 3/12/2020 ALDOUS CHIC
Issued 3/16/2020 LADBS
CofO in Progress 4/7/2023 ROBERT DAVIS
Permit Finaled 4/18/2023 JEFFREY DURAN
CofO Issued 4/18/2023 JEFFREY DURAN
Permit Finaled 4/18/2023 JEFFREY DURAN

Permit Application Clearance Information

Miscellaneous Cleared 2/24/2020 DANG NGUYEN
ZI Cleared 2/24/2020 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 2/25/2020 JOHN LIN
Sewer availability Cleared 2/25/2020 JOHN LIN
Public Works-Highway Ded. Cleared 2/25/2020 JOHN LIN
Public Works-Open Permits Cleared 2/25/2020 JOHN LIN
Public Works-Sewers Cleared 2/25/2020 JOHN LIN
"Q" conditions Cleared 2/27/2020 MIGUEL GAMBOA
Comm Cor/Mini-Mall Cleared 2/27/2020 MIGUEL GAMBOA
Specific Plan Cleared 3/6/2020 OLGA AYALA
ZI Cleared 3/6/2020 OLGA AYALA
Redevelopment Project Area Cleared 3/12/2020 MIGUEL GAMBOA

Contact Information

Contractor Globus Builder Inc; Lic. No.: 961380-B 6350 LAUREL CANYON BLVD   SUITE 400    NORTH HOLLYWOOD, CA 91606
Engineer Charifa,, Rizaldy Dizon; Lic. No.: C62585 815 W CESAR E CHAVEZ AVE STE 205      LOS ANGELES, CA 90012

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 4/8/2020 Conditional Approval ROBERT DAVIS
Drywall Nailing 4/27/2020 Approved ROBERT DAVIS
Pre-Inspection 6/29/2020 Not Ready for Inspection ROBERT DAVIS
Final 3/20/2023 OK to Issue CofO ROBERT DAVIS
Reinforced Concrete Frame 3/20/2023 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV Approved ROBERT DAVIS
Smoke Detectors 3/20/2023 Approved ROBERT DAVIS