17447-17449 W LUDLOW ST 91344

Certificate Information: 17447-17449 W LUDLOW ST 91344

Application / Permit
20016-20000-04729
Plan Check / Job No.
B20VN02695
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert the attached garage into an Accessory Dwelling Unit
Permit Issued
Issued on 2/26/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2020 APPLICANT
Assigned to Plan Check Engineer 2/18/2020 YAQUB MIRZA
Corrections Issued 2/18/2020 YAQUB MIRZA
Plan Check Approved 2/18/2020 ANGELICA MARTINEZ
Issued 2/26/2020 LADBS
CofO in Progress 8/12/2020 DAVID SCANTLIN
CofO Issued 8/17/2020 DONALD SUNSERI
Permit Finaled 8/17/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 2/18/2020 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 2/18/2020 APEKSHYA BAJRACHARYA
Sewer availability Cleared 2/18/2020 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/27/2020 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 6/4/2020 Approved DAVID SCANTLIN
PLUMBING-Rough 6/4/2020 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 6/10/2020 Approved DAVID SCANTLIN
Footing/Foundation/Slab 6/10/2020 Approved DAVID SCANTLIN
Green Building Rough 6/10/2020 Approved DAVID SCANTLIN
HVAC-Rough 6/10/2020 Approved DAVID SCANTLIN
Insulation 6/12/2020 Approved DAVID SCANTLIN
Drywall Nailing 6/25/2020 Approved DAVID SCANTLIN
Interior/Exterior Lathing 7/1/2020 Approved DAVID SCANTLIN
ELECTRICAL-Final 8/11/2020 Approved DAVID SCANTLIN
Final 8/11/2020 OK to Issue CofO DAVID SCANTLIN
Green Building Final 8/11/2020 Approved DAVID SCANTLIN
HVAC-Final 8/11/2020 Approved DAVID SCANTLIN
PLUMBING-Final 8/11/2020 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 8/11/2020 SGSOV Approved DAVID SCANTLIN
Service/Power Release 8/11/2020 Approved DAVID SCANTLIN
Smoke Detectors 8/11/2020 Approved DAVID SCANTLIN