2139 S REDONDO BLVD 90016
Certificate Information: 2139 S REDONDO BLVD 90016
- Application / Permit
- 20016-20000-04648
- Plan Check / Job No.
- B20VN02664
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-3" X 18'-3" DETACHED GARAGE TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 7/31/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2020 | ALDOUS CHIC |
| Corrections Issued | 2/18/2020 | ALDOUS CHIC |
| Building Plans Picked Up | 2/28/2020 | APPLICANT |
| Plan Check Approved | 7/8/2020 | RAPHAEL ROSAS |
| Issued | 7/31/2020 | APPLICANT |
| CofO in Progress | 12/10/2020 | DAVID CHAN |
| Permit Finaled | 2/3/2021 | DEROLD HAUFF |
| CofO Issued | 2/3/2021 | DEROLD HAUFF |
| Permit Finaled | 2/3/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 4/24/2020 | CYNTHIA RYAN |
| Address approval | Cleared | 5/4/2020 | WALLIE JONG |
| Sewer availability | Cleared | 5/4/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2020 | WALLIE JONG |
| Construction near power lines | Cleared | 7/7/2020 | OSCAR CASTRO |
Contact Information
| Contractor | Dreamworks Builders; Lic. No.: 1052079-B | 22647 VENTURA BLVE SUITE 586 WOODLAND HILLS, CA 91364 |
| Engineer | , ; Lic. No.: CEG89006 | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/3/2020 | Approved | MATTHEW NUCKOLLS |
| Excavation/Setback/Form/Re-Bar | 8/20/2020 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 8/20/2020 | Corrections Issued | DAVID CHAN |
| Sewer | 8/20/2020 | Partial Approval | DAVID CHAN |
| Deputy Drilled-In Anchors | 8/25/2020 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/25/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 8/25/2020 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2020 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 9/8/2020 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/16/2020 | Not Ready for Inspection | DAVID CHAN |
| Interior/Exterior Lathing | 9/16/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 9/29/2020 | Partial Approval | DAVID CHAN |
| Rough-Elec/Plmb/HVAC | 9/29/2020 | Partial Approval | DAVID CHAN |
| Shower Pan | 9/29/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 10/2/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| ELECTRICAL-Rough | 10/2/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| Green Building Rough | 10/2/2020 | Approved | DONALD CRICHLOW |
| PLUMBING-Rough | 10/2/2020 | Corrections Issued | DONALD CRICHLOW |
| Rough-Elec/Plmb/HVAC | 10/6/2020 | Approved | DONALD CRICHLOW |
| Wood Frame | 10/6/2020 | Approved | DONALD CRICHLOW |
| Drywall Nailing | 10/13/2020 | Approved | DAVID CHAN |
| Insulation | 10/13/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 11/18/2020 | Approved | DAVID CHAN |
| Final | 11/18/2020 | Corrections Issued | DAVID CHAN |
| Green Building Final | 11/18/2020 | Approved | DAVID CHAN |
| HVAC-Rough | 11/18/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV Not Ready | DAVID CHAN |
| Smoke Detectors | 11/18/2020 | Approved | DAVID CHAN |
| Final | 12/8/2020 | OK to Issue CofO | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2020 | SGSOV Approved | DAVID CHAN |