17558 W HAMLIN ST 91406

Certificate Information: 17558 W HAMLIN ST 91406

Application / Permit
20016-20000-04607
Plan Check / Job No.
B20VN02645
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT. See comment
Permit Issued
Issued on 2/28/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2020 APPLICANT
Assigned to Plan Check Engineer 2/15/2020 ALDOUS CHIC
Corrections Issued 2/18/2020 ALDOUS CHIC
Building Plans Picked Up 2/18/2020 APPLICANT
Plan Check Approved 2/28/2020 ALDOUS CHIC
Issued 2/28/2020 LADBS
CofO in Progress 5/29/2020 STEVEN BACK
CofO in Progress 5/29/2020 STEVEN BACK
CofO in Progress 6/18/2020 STEVEN BACK
CofO Issued 7/9/2020 DONALD SUNSERI
Permit Finaled 7/9/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 2/19/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 2/19/2020 EMIL KYUPELYAN
Sewer availability Cleared 2/19/2020 EMIL KYUPELYAN

Contact Information

Contractor E H D Builders Inc; Lic. No.: 1034101-B 18375 VENTURA BLVD 122      TARZANA, CA 91356

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/18/2020 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 3/18/2020 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 3/18/2020 Corrections Issued STEVEN BACK
Pre-Inspection 3/18/2020 Approved STEVEN BACK
Sewer 3/18/2020 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 3/23/2020 Corrections Issued STEVEN BACK
PLUMBING-Rough 3/23/2020 Partial Approval STEVEN BACK
Sewer 3/23/2020 Approved STEVEN BACK
Footing/Foundation/Slab 3/25/2020 Approved STEVEN BACK
Excavation/Setback/Form/Re-Bar 3/26/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 4/14/2020 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 4/14/2020 Partial Approval STEVEN BACK
HVAC-Rough 4/14/2020 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 4/14/2020 Approved STEVEN BACK
HVAC-Rough 4/15/2020 Approved STEVEN BACK
Special/Order Compliance 4/15/2020 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 4/17/2020 Approved STEVEN BACK
ELECTRICAL-Rough 4/17/2020 Approved STEVEN BACK
Green Building Rough 4/17/2020 Approved STEVEN BACK
Insulation 4/17/2020 Approved STEVEN BACK
Special/Order Compliance 4/17/2020 Approved STEVEN BACK
Drywall Nailing 4/20/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/20/2020 Approved STEVEN BACK
Interior/Exterior Lathing 4/20/2020 Approved STEVEN BACK
Interior/Exterior Lathing 4/27/2020 Approved STEVEN BACK
Final 5/22/2020 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/22/2020 SGSOV Not Ready STEVEN BACK
Smoke Detectors 5/22/2020 Approved STEVEN BACK
ELECTRICAL-Final 5/27/2020 Corrections Issued STEVEN BACK
HVAC-Final 5/27/2020 Corrections Issued STEVEN BACK
PLUMBING-Final 5/27/2020 Approved STEVEN BACK
Final 5/29/2020 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/29/2020 SGSOV Approved STEVEN BACK
Final 6/4/2020 Corrections Issued STEVEN BACK
Final 6/15/2020 Not Ready for Inspection STEVEN BACK
Final 6/18/2020 OK to Issue CofO STEVEN BACK