1156 S STEARNS DR 90035
Certificate Information: 1156 S STEARNS DR 90035
- Application / Permit
- 20016-20000-04527
- Plan Check / Job No.
- B20VN02591
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETAHCED GARAGE TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2020 | ALDOUS CHIC |
| Corrections Issued | 2/14/2020 | ALDOUS CHIC |
| Plan Check Approved | 2/24/2020 | ALDOUS CHIC |
| Issued | 2/24/2020 | LADBS |
| CofO in Progress | 6/18/2020 | DAVID CHAN |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 2/14/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/14/2020 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 2/19/2020 | WALTER RAMIREZ |
| HPOZ | Cleared | 2/19/2020 | JONATHAN KAPLAN |
| Miscellaneous | Cleared | 2/19/2020 | JONATHAN KAPLAN |
| Miscellaneous | Cleared | 2/19/2020 | JONATHAN KAPLAN |
| ZI | Cleared | 2/19/2020 | JONATHAN KAPLAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lerner, George; Lic. No.: C40288 | 4668 WILLIS AVE SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/2/2020 | Partial Approval | DAVID CHAN |
| Shower Pan | 3/9/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 3/16/2020 | Partial Approval | MATTHEW NUCKOLLS |
| BUILDING-Rough-Frame | 5/28/2020 | Approved | DAVID CHAN |
| Final | 5/28/2020 | Corrections Issued | DAVID CHAN |
| Green Building Final | 5/28/2020 | Approved | DAVID CHAN |
| Green Building Rough | 5/28/2020 | Approved | DAVID CHAN |
| METHANE-Final | 5/28/2020 | Approved | DAVID CHAN |
| METHANE-Rough | 5/28/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 5/28/2020 | SGSOV Not Ready | DAVID CHAN |
| Smoke Detectors | 5/28/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Final | 6/11/2020 | Approved | DAVID CHAN |
| Final | 6/11/2020 | OK to Issue CofO | DAVID CHAN |
| HVAC-Final | 6/11/2020 | Approved | DAVID CHAN |
| PLUMBING-Final | 6/11/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 6/11/2020 | SGSOV Approved | DAVID CHAN |