900-902 S DETROIT ST 90036

Certificate Information: 900-902 S DETROIT ST 90036

Application / Permit
20016-20000-04373
Plan Check / Job No.
B20VN02521
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
REMOVE (E) DAMAGED EXTERIOR STAIRS AND ADD 16'-0" X 38'-6" IRREG SHAPED COVERED PATIO W/ DECK ABOVE AT REAR OF (E) DUPLEX
Permit Issued
Issued on 5/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 JEROME MAGAT PALMA
Corrections Issued 3/9/2020 JEROME MAGAT PALMA
Quality Review Completed 3/10/2020 ABDUL CHEGENI
Building Plans Picked Up 3/12/2020 APPLICANT
Plan Check Approved 4/1/2020 JEROME MAGAT PALMA
Issued 5/12/2020 LADBS
CofO in Progress 11/3/2021 ARTHUR SARGSYAN
Permit Finaled 11/10/2021 DEROLD HAUFF
CofO Issued 11/10/2021 DEROLD HAUFF
Permit Finaled 11/10/2021 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 3/16/2020 LAUREN PADICK
Tenant Habitability Plan Cleared 3/19/2020 PHILLIP MUNGUIA
HPOZ Cleared 3/26/2020 DANIEL MATA
ZI Cleared 3/26/2020 DANIEL MATA

Contact Information

Contractor Davids Crew Inc; Lic. No.: 902629-B 1320 KELLAM AVE      LOS ANGELES, CA 90026

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/22/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/22/2021 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 7/23/2021 No Access for Inspection ELMER BLAND
Deputy Reinf. Concrete 7/30/2021 Approved ARTHUR SARGSYAN
Deputy Reinf. Concrete 8/20/2021 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 8/20/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 8/20/2021 Approved ARTHUR SARGSYAN
Structural Steel Frame 8/20/2021 Approved ARTHUR SARGSYAN
Deputy Reinf. Concrete 8/23/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Approved ARTHUR SARGSYAN
METHANE-Rough 9/2/2021 Approved ARTHUR SARGSYAN
Wood Frame 9/2/2021 Approved ARTHUR SARGSYAN
Final 10/19/2021 Conditional Approval ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/19/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 10/19/2021 Approved ARTHUR SARGSYAN