5218 N FULTON AVE 91401

Certificate Information: 5218 N FULTON AVE 91401

Application / Permit
20016-20000-04352
Plan Check / Job No.
B20VN02501
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET. REC ROOM AND ADD (E) (20'-0" x 20'-3") IRR SHAPE CONFINED SPACE TO ACCESSORY DWELLING UNIT. WORK PER LA STD WFPP.
Permit Issued
Issued on 3/18/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2020 APPLICANT
Assigned to Plan Check Engineer 2/14/2020 TROY DEGUZMAN
Corrections Issued 2/17/2020 TROY DEGUZMAN
Building Plans Picked Up 2/19/2020 APPLICANT
Plan Check Approved 3/17/2020 TROY DEGUZMAN
Issued 3/18/2020 LADBS
CofO in Progress 5/5/2021 MICHAEL TEMPLE
Permit Finaled 5/22/2021 MICHAEL SMITH
CofO Issued 5/22/2021 MICHAEL SMITH
Permit Finaled 5/22/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/20/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 2/20/2020 GUILLERMO PETRA
Sewer availability Cleared 3/17/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/12/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 2/3/2021 Partial Approval BRENDAN LOONEY
Special/Order Compliance 2/22/2021 Partial Approval MATTHEW NELSON
Final 3/15/2021 Not Ready for Inspection CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Not Ready CHARLES POWELL
Smoke Detectors 3/15/2021 Not Ready for Inspection CHARLES POWELL
Wood Frame 3/15/2021 Not Ready for Inspection CHARLES POWELL
Final 3/18/2021 Corrections Issued BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 3/18/2021 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 3/18/2021 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 3/18/2021 Approved BRENDAN LOONEY
Final 4/14/2021 Partial Approval RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 4/14/2021 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 4/14/2021 Approved RICHARD DOCKUS
Final 4/22/2021 Not Ready for Inspection RICHARD DOCKUS
Final 5/4/2021 OK to Issue CofO MICHAEL TEMPLE