7637 N GENESTA AVE 91406
Certificate Information: 7637 N GENESTA AVE 91406
- Application / Permit
- 20016-20000-04335
- Plan Check / Job No.
- B20VN02484
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) (18' X 50') DET. GARAGE TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2020 | RAPHAEL ROSAS |
| Corrections Issued | 2/18/2020 | RAPHAEL ROSAS |
| Building Plans Picked Up | 2/19/2020 | APPLICANT |
| Issued | 2/24/2020 | LADBS |
| CofO in Progress | 4/19/2021 | ARTHUR SARGSYAN |
| CofO Issued | 6/12/2021 | MICHAEL SMITH |
| Permit Finaled | 6/12/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 2/20/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/20/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/8/2020 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 4/14/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 4/14/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 4/14/2020 | No Access for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 4/14/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 4/15/2020 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 4/16/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/16/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 4/16/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 4/24/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 6/5/2020 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 6/5/2020 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 6/5/2020 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 6/12/2020 | No Access for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 6/12/2020 | Not Ready for Inspection | JOHN HAYES |
| Gas Test | 6/12/2020 | No Access for Inspection | JOHN HAYES |
| Green Building Rough | 6/12/2020 | No Access for Inspection | JOHN HAYES |
| HVAC-Rough | 6/12/2020 | No Access for Inspection | JOHN HAYES |
| PLUMBING-Rough | 6/12/2020 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 6/15/2020 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 6/15/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/15/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/20/2020 | Approved | JOHN HAYES |
| Green Building Rough | 7/20/2020 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 7/20/2020 | Approved | JOHN HAYES |
| Insulation | 8/4/2020 | Corrections Issued | DONALD SUNSERI |
| Insulation | 8/12/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/12/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/18/2020 | Approved | DONALD SUNSERI |
| ELECTRICAL-Final | 9/8/2020 | Corrections Issued | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 9/8/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Service/Power Release | 9/8/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Special/Order Compliance | 9/8/2020 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 9/14/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/22/2020 | Partial Inspection | MISAEL ESPARZA |
| Final | 3/5/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Green Building Final | 3/5/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/5/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 3/5/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 4/5/2021 | Approved | ARTHUR SARGSYAN |
| Final | 4/5/2021 | OK to Issue CofO | ARTHUR SARGSYAN |
| Green Building Final | 4/5/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 4/5/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 4/5/2021 | Approved | ARTHUR SARGSYAN |
| Final | 4/8/2021 | Corrections Issued | ARTHUR SARGSYAN |