9850 N ZELZAH AVE #101 91325

Certificate Information: 9850 N ZELZAH AVE #101 91325

Application / Permit
20016-20000-04219
Plan Check / Job No.
B20VN02441
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT (E) RECREATION ROOM & PORTION OF OFFICE TO ACCESSORY DWELLING UNIT WITHIN EX. APARTMENT BLDG.
Permit Issued
Issued on 4/20/2021
Issuing Office
Current Status
CofO Issued on 12/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 JEFFREY TANGONAN
Corrections Issued 3/9/2020 JEFFREY TANGONAN
Quality Review Completed 3/10/2020 STEVEN KIM
Building Plans Picked Up 3/12/2020 APPLICANT
Plan Check Approved 7/10/2020 JEFFREY TANGONAN
Issued 4/20/2021 APPLICANT
CofO in Progress 12/15/2021 JEFFREY FULTON
CofO Issued 12/15/2021 JEFFREY DURAN
Permit Finaled 12/15/2021 JEFFREY DURAN

Permit Application Clearance Information

"Q" conditions Cleared 4/28/2020 LAUREN PADICK
Miscellaneous Cleared 4/28/2020 LAUREN PADICK
ZA Case Cleared 4/28/2020 LAUREN PADICK
Address approval Cleared 5/22/2020 ADRIAN CASTRO
Sewer availability Cleared 5/22/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/29/2020 ADRIAN CASTRO

Contact Information

Contractor Consolidated Porperty Services Inc; Lic. No.: 696921-B 4730 WOODMAN AVE STE 200      SHERMAN OAKS, CA 91423

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/28/2021 Corrections Issued JEFFREY FULTON
Drywall Nailing 10/14/2021 Not Ready for Inspection JEFFREY FULTON
Final 10/14/2021 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 10/14/2021 Corrections Issued JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 10/14/2021 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 11/15/2021 Approved JONATHAN QUACH
Drywall Nailing 11/18/2021 Approved JEFFREY FULTON
Final 11/24/2021 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 11/24/2021 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 11/24/2021 Not Ready for Inspection JEFFREY FULTON
Wood Frame 11/24/2021 Approved JEFFREY FULTON
Final 11/30/2021 OK to Issue CofO JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Approved JEFFREY FULTON
Smoke Detectors 11/30/2021 Approved JEFFREY FULTON