23738 W VANOWEN ST 91307
Certificate Information: 23738 W VANOWEN ST 91307
- Application / Permit
- 20016-20000-04206
- Plan Check / Job No.
- B20VN02431
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 21' X 21' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A). WORK PER ENGINEER.
- Permit Issued
- Issued on 11/10/2020
- Issuing Office
- Current Status
- CofO Issued on 4/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2020 | JENNIFER LEE |
| Corrections Issued | 2/21/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 3/25/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 4/30/2020 | JENNIFER LEE |
| No Progress | 7/30/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/19/2020 | HAYATO TSUCHIYA |
| Issued | 11/10/2020 | APPLICANT |
| CofO in Progress | 3/26/2021 | TROY SANDERS |
| Permit Finaled | 4/8/2021 | JOHN JANSON |
| CofO Issued | 4/8/2021 | JOHN JANSON |
| Permit Finaled | 4/8/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/21/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/21/2020 | GUILLERMO PETRA |
Contact Information
| Architect | Rocha,, Carlos Joel; Lic. No.: C19775 | 28025 DOROTHY DRIVE SUITE 206 AGOURA HILLS, CA 91301 |
| Contractor | Rocha Nuez Abdoh Construction Inc; Lic. No.: 791474-B | 28025 DOROTHY DRIVE #100 AGOURA HILLS, CA 91301 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/3/2020 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 12/3/2020 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 12/3/2020 | Approved | TROY SANDERS |
| Gas Test | 12/3/2020 | Approved | TROY SANDERS |
| Green Building Rough | 12/3/2020 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 12/3/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 12/10/2020 | Approved | TROY SANDERS |
| HVAC-Rough | 12/10/2020 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Approved | TROY SANDERS |
| Drywall Nailing | 12/23/2020 | Approved | TROY SANDERS |
| Green Building Rough | 12/23/2020 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 12/23/2020 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 3/15/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 3/15/2021 | Approved | TROY SANDERS |
| Final | 3/15/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 3/15/2021 | Corrections Issued | TROY SANDERS |
| HVAC-Final | 3/15/2021 | Approved | TROY SANDERS |
| PLUMBING-Final | 3/15/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/15/2021 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 3/15/2021 | Approved | TROY SANDERS |
| Underground Mechanical | 3/15/2021 | Approved | TROY SANDERS |
| Final | 3/26/2021 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 3/26/2021 | Approved | TROY SANDERS |