10317 W LORNE ST 91352

Certificate Information: 10317 W LORNE ST 91352

Application / Permit
20016-20000-03932
Plan Check / Job No.
B20VN02249
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) (22'-2"x 20'-2") DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LA STD WFPP.
Permit Issued
Issued on 2/25/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2020 APPLICANT
Assigned to Plan Check Engineer 2/11/2020 TROY DEGUZMAN
Corrections Issued 2/11/2020 TROY DEGUZMAN
Building Plans Picked Up 2/12/2020 APPLICANT
Plan Check Approved 2/25/2020 TROY DEGUZMAN
Issued 2/25/2020 LADBS
CofO in Progress 11/20/2020 BEAU COLLINS
CofO Issued 2/13/2021 MICHAEL SMITH
Permit Finaled 2/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/12/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/12/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 2/12/2020 ADRIAN CASTRO
Sewer availability Cleared 2/12/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/12/2020 No Access for Inspection BEAU COLLINS
PLUMBING-Rough 3/24/2020 Not Ready for Inspection BEAU COLLINS
PLUMBING-Rough 4/1/2020 Partial Approval BEAU COLLINS
ELECTRICAL-Rough 5/18/2020 Approved BEAU COLLINS
PLUMBING-Rough 5/18/2020 Corrections Issued BEAU COLLINS
Sewer 5/18/2020 Approved BEAU COLLINS
BUILDING-Rough-Frame 5/27/2020 Approved BEAU COLLINS
Green Building Rough 5/27/2020 Approved BEAU COLLINS
MERV13>=Rough 5/27/2020 Approved BEAU COLLINS
Rough-Elec/Plmb/HVAC 5/27/2020 Approved BEAU COLLINS
Insulation 6/3/2020 Approved BEAU COLLINS
Drywall Nailing 6/10/2020 Approved BEAU COLLINS
Final 8/13/2020 Corrections Issued BEAU COLLINS
Final 10/7/2020 Corrections Issued JOHN HAYES
Green Building Final 10/7/2020 Not Ready for Inspection JOHN HAYES
MERV13>=Final 10/7/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 10/7/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 10/7/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 11/18/2020 Approved BEAU COLLINS
Final 11/20/2020 OK to Issue CofO BEAU COLLINS
Green Building Final 11/20/2020 Approved BEAU COLLINS
MERV13>=Final 11/20/2020 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 11/20/2020 SGSOV Approved BEAU COLLINS
Smoke Detectors 11/20/2020 Approved BEAU COLLINS