6110 N VARIEL AVE 91367
Certificate Information: 6110 N VARIEL AVE 91367
- Application / Permit
- 20016-20000-03912
- Plan Check / Job No.
- B20VN02240
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Day Care Facility adults
- Work Description
- CONVERT 13,719 SF PORTION OF FIRST FLOOR OFFICE TO ADULT DAY CARE FACILITY
- Permit Issued
- Issued on 3/17/2021
- Issuing Office
- Current Status
- CofO Issued on 7/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | JEFFREY TANGONAN |
| Corrections Issued | 3/3/2020 | JEFFREY TANGONAN |
| Quality Review Completed | 3/3/2020 | STEVEN KIM |
| Disabled Access Plans Picked Up | 3/4/2020 | APPLICANT |
| Green Plans Picked Up | 3/4/2020 | APPLICANT |
| Applicant returned to address corrections | 8/6/2020 | JEFFREY TANGONAN |
| Plan Check Approved | 2/19/2021 | JEFFREY TANGONAN |
| Plan Check Approved | 3/17/2021 | JEFFREY TANGONAN |
| Issued | 3/17/2021 | APPLICANT |
| Building Plans Picked Up | 3/19/2021 | APPLICANT |
| CofO in Progress | 7/6/2021 | CAMERON CHABAN |
| Permit Finaled | 7/8/2021 | JEFFREY DURAN |
| CofO Issued | 7/8/2021 | JEFFREY DURAN |
| Permit Finaled | 7/8/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/4/2020 | STEVEN WECHSLER |
| Green Code | Cleared | 4/7/2020 | DAVID MATSON |
| DAS Clearance | Cleared | 4/30/2020 | JEFFREY TANGONAN |
| Address approval | Cleared | 5/12/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/13/2020 | GABRIEL ROBLES |
| Fire Marshall Fire Life Safety | Cleared | 6/24/2020 | MENOA AGHAJANI |
| Specific Plan | Cleared | 1/26/2021 | LAUREN PADICK |
Contact Information
| Contractor | Superior Design & Construction; Lic. No.: 867041-B | 23800 BERDON STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 3/19/2021 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 4/19/2021 | Approved | JEFFREY FULTON |
| Final | 6/4/2021 | Not Ready for Inspection | CAMERON CHABAN |
| Green Building Final | 6/4/2021 | Not Ready for Inspection | CAMERON CHABAN |
| Green Building Rough | 6/4/2021 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 6/4/2021 | SGSOV Not Ready | CAMERON CHABAN |
| Smoke Detectors | 6/4/2021 | Approved | CAMERON CHABAN |
| Wood Frame | 6/4/2021 | Not Ready for Inspection | CAMERON CHABAN |
| Final | 6/9/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Final | 6/9/2021 | Approved | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/9/2021 | SGSOV No Gas | DANIEL VARNUM |
| Wood Frame | 6/9/2021 | No Access for Inspection | DANIEL VARNUM |
| Special/Order Compliance | 6/11/2021 | Partial Inspection | CAMERON CHABAN |
| Final | 6/24/2021 | OK to Issue CofO | CAMERON CHABAN |
| Wood Frame | 6/24/2021 | Approved | CAMERON CHABAN |