9561-9563 N FARRALONE AVE 91311
Certificate Information: 9561-9563 N FARRALONE AVE 91311
- Application / Permit
- 20016-20000-03738
- Plan Check / Job No.
- B20VN02133
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 24' X 20' (445 SQ.FT.) ATTACHED GARAGE TO (E) SFD TO NEW JUNIOR ACCESSORY DWELLING UNIT , ALL WORK PER WFPP - SEE COMMENTS
- Permit Issued
- Issued on 4/21/2020
- Issuing Office
- Current Status
- CofO Issued on 7/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2020 | APPLICANT |
| Green Plans Picked Up | 3/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | RARES BODEA |
| Corrections Issued | 3/19/2020 | RARES BODEA |
| Quality Review Completed | 3/19/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/24/2020 | APPLICANT |
| Applicant returned to address corrections | 4/2/2020 | RARES BODEA |
| Plan Check Approved | 4/21/2020 | RARES BODEA |
| Issued | 4/21/2020 | APPLICANT |
| CofO in Progress | 7/20/2020 | DAVID STEPANYAN |
| CofO Issued | 7/21/2020 | JOHN JANSON |
| Permit Finaled | 7/21/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2020 | ROSE MARIE SMITH |
| Sewer availability | Cleared | 3/26/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 4/2/2020 | MICHAEL AYERS |
| Grading Pre-Inspection | Cleared | 4/13/2020 | TIMOTHY POWELL |
| Miscellaneous | Cleared | 4/20/2020 | RARES BODEA |
| Specific Plan | Cleared | 4/20/2020 | WILLIAM CABRERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2020 | Partial Approval | DAVID STEPANYAN |
| Underground Mechanical | 5/6/2020 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 5/11/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/3/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 6/3/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 6/3/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 6/3/2020 | Approved | DAVID STEPANYAN |
| Insulation | 6/3/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 6/3/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 6/3/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2020 | SGSOV Approved | DAVID STEPANYAN |
| Shower Pan | 6/3/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 6/3/2020 | Partial Approval | DAVID STEPANYAN |
| Drywall Nailing | 6/8/2020 | Approved | DAVID STEPANYAN |
| Gas Test | 6/8/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Final | 6/25/2020 | Corrections Issued | DAVID STEPANYAN |
| Final | 6/25/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 6/25/2020 | Approved | DAVID STEPANYAN |
| HVAC-Final | 6/25/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 6/25/2020 | Approved | DAVID STEPANYAN |
| Smoke Detectors | 6/25/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 6/29/2020 | Approved | DAVID STEPANYAN |
| Gas Test | 6/29/2020 | Approved | DAVID STEPANYAN |
| Final | 7/15/2020 | Corrections Issued | DAVID STEPANYAN |
| Final | 7/20/2020 | OK to Issue CofO | DAVID STEPANYAN |