446-446 1/2 E 42ND PL 90011
Certificate Information: 446-446 1/2 E 42ND PL 90011
- Application / Permit
- 20016-20000-03565
- Plan Check / Job No.
- B20VN02006
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 20' X 13' ADDITION TO AND CONVERT (E) 16'4" X 20' PORTION OF (E) SFD TO ACCESSORY DWELLING UNIT AS PER LAMC12.22.A.33(C) AND (E) , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/21/2021
- Issuing Office
- Current Status
- CofO Issued on 9/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | RARES BODEA |
| Corrections Issued | 3/20/2020 | RARES BODEA |
| Quality Review Completed | 4/2/2020 | STEVEN KIM |
| Building Plans Picked Up | 5/20/2020 | APPLICANT |
| Plan Check Approved | 3/23/2021 | RARES BODEA |
| Issued | 4/21/2021 | APPLICANT |
| CofO in Progress | 9/13/2022 | ANTHONY EGSON |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
| CofO Issued | 9/16/2022 | DEROLD HAUFF |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/20/2020 | SHEILA GERSHON |
| Roof/Waste drainage to street | Cleared | 7/31/2020 | WALLIE JONG |
| Sewer availability | Cleared | 8/5/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2020 | PAMELA TENEZA |
| Address approval | Cleared | 10/2/2020 | JAMES KHO |
| Tenant Habitability Plan | Cleared | 3/18/2021 | RICHARD BRINSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sadjadi,, Abdulreza; Lic. No.: C51812 | 1223 WILSHIRE BLVD #169 SANTA MONICA, CA 90403 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/3/2021 | Not Ready for Inspection | SABAS ALONSO |
| Pre-Inspection | 8/2/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/3/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/10/2021 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 11/15/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 11/19/2021 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2021 | Partial Approval | SHAVONNE ESPINOZA |
| Green Building Rough | 12/29/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Insulation | 12/29/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 1/5/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/10/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 3/10/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 3/10/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/10/2022 | Approved | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 3/14/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/22/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 3/22/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 3/22/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/22/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 4/22/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 4/25/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 5/11/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 5/11/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 5/20/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 6/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 6/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 7/27/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/27/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 7/27/2022 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 7/27/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 7/28/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 8/5/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 9/1/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 9/13/2022 | OK to Issue CofO | ANTHONY EGSON |