10300 N SEPULVEDA BLVD 91345

Certificate Information: 10300 N SEPULVEDA BLVD 91345

Application / Permit
20016-20000-03501
Plan Check / Job No.
B20VN01967
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Bank
Work Description
TENANT IMPROVEMENT TO (E) BANK
Permit Issued
Issued on 11/16/2020
Issuing Office
Current Status
Permit Finaled on 5/14/2021

Permit Application Status History

Submitted 2/5/2020 APPLICANT
Green Plans Picked Up 2/20/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 RAPHAEL ROSAS
Corrections Issued 3/2/2020 RAPHAEL ROSAS
Quality Review Completed 3/6/2020 CHON CHIO KUO
Building Plans Picked Up 3/10/2020 APPLICANT
Disabled Access Plans Picked Up 3/17/2020 APPLICANT
Plan Check Approved 10/26/2020 RAPHAEL ROSAS
Issued 11/16/2020 APPLICANT
Permit Finaled 5/14/2021 ANDREW DORSO

Permit Application Clearance Information

Green Code Cleared 7/24/2020 MICHAEL AYERS
DAS Clearance Cleared 10/8/2020 RAPHAEL ROSAS

Contact Information

Architect Stapleton,, James Dennis; Lic. No.: C24471 3339 BISHOP ST AVE      CINCINNATI, OH 45220
Contractor Excel Construction Services Inc; Lic. No.: 852879-B 1950 RAYMER AVENUE      FULLERTON, CA 92833
Engineer Thorpe,, William Howard; Lic. No.: S3866 1649 PALAU PLACE      COSTA MESA, CA 92626

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 1/22/2021 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 1/22/2021 Not Ready for Inspection ANDREW DORSO
Insulation 1/22/2021 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 1/22/2021 Partial Inspection ANDREW DORSO
Drywall Nailing 2/1/2021 Partial Inspection ANDREW DORSO
T-Bar Ceiling 2/9/2021 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 2/25/2021 Approved ANDREW DORSO
Light Gage Steel Frame 3/2/2021 Partial Inspection ANDREW DORSO
Drywall Nailing 3/5/2021 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 3/12/2021 Partial Inspection ANDREW DORSO
Drywall Nailing 3/15/2021 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 3/15/2021 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 3/24/2021 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 3/24/2021 Approved ANDREW DORSO
Drywall Nailing 3/26/2021 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 3/26/2021 Approved ROBERT DAVIS
Drywall Nailing 3/30/2021 Approved ROBERT DAVIS
Final 5/14/2021 Permit Finaled ANDREW DORSO
Green Building Final 5/14/2021 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 5/14/2021 SGSOV Approved ANDREW DORSO
Smoke Detectors 5/14/2021 Approved ANDREW DORSO