4600 N ARRIBA DR 91356
Certificate Information: 4600 N ARRIBA DR 91356
- Application / Permit
- 20016-20000-03479
- Plan Check / Job No.
- B20VN01948
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL, 7'-7" X 7'-11" LAUNDRY ADDITION, REMODEL (E) KITCHEN IN (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/16/2020
- Issuing Office
- Current Status
- CofO Issued on 2/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 2/5/2020 | ARTIN ZARUKIAN |
| Plan Check Approved | 9/4/2020 | RAPHAEL ROSAS |
| Issued | 9/16/2020 | APPLICANT |
| CofO in Progress | 1/11/2022 | DAVID SANDOVAL |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
| CofO Issued | 2/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2020 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 2/7/2020 | BARTON HOLMES |
| Roof/Waste drainage to street | Cleared | 2/7/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Finesse Remodeling & Consulting Inc; Lic. No.: 932094-B | 4600 ARIBA DRIVE TARZANA, CA 91356 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/2/2020 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/6/2020 | Partial Approval | HENRY KIM |
| Underground Mechanical | 10/6/2020 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 10/20/2020 | Corrections Issued | MICHAEL TEMPLE |
| Rough-Elec/Plmb/HVAC | 10/20/2020 | Corrections Issued | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 10/26/2020 | Approved | DAVID SANDOVAL |
| Green Building Rough | 10/26/2020 | Approved | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 10/26/2020 | Approved | DAVID SANDOVAL |
| Insulation | 10/30/2020 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 10/30/2020 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 11/6/2020 | Approved | DAVID SANDOVAL |
| Final | 4/13/2021 | Corrections Issued | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 4/13/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 10/7/2021 | Corrections Issued | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 10/7/2021 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 10/7/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 10/19/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Smoke Detectors | 10/19/2021 | Approved | DAVID SANDOVAL |
| Final | 1/11/2022 | OK to Issue CofO | DAVID SANDOVAL |