2119 S SPAULDING AVE 90016

Certificate Information: 2119 S SPAULDING AVE 90016

Application / Permit
20016-20000-03461
Plan Check / Job No.
B20VN01937
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 5/21/2020
Issuing Office
Current Status
CofO Issued on 2/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2020 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 HAYATO TSUCHIYA
Corrections Issued 2/7/2020 HAYATO TSUCHIYA
Building Plans Picked Up 2/10/2020 APPLICANT
Applicant returned to address corrections 4/8/2020 HAYATO TSUCHIYA
Plan Check Approved 4/25/2020 HAYATO TSUCHIYA
Plan Check Approved 4/28/2020 HAYATO TSUCHIYA
Issued 5/21/2020 APPLICANT
CofO in Progress 9/23/2020 DAVID CHAN
Permit Finaled 2/17/2023 DANIEL ORRANTE
CofO Issued 2/17/2023 DANIEL ORRANTE
Permit Finaled 2/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/10/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/10/2020 ADRIAN CASTRO
Sewer availability Cleared 2/10/2020 ADRIAN CASTRO
Construction near power lines Cleared 3/9/2020 OSCAR CASTRO
Construction within easement Cleared 3/9/2020 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 5525 CANOGA AVE APT 208      WOODLAND HILLS, CA 91367

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/26/2020 Approved DAVID CHAN
PLUMBING-Rough 5/26/2020 Not Ready for Inspection DAVID CHAN
Drywall Nailing 6/2/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 6/2/2020 Corrections Issued DAVID CHAN
BUILDING-Rough-Frame 6/16/2020 Approved DAVID CHAN
Green Building Rough 6/16/2020 Approved DAVID CHAN
PLUMBING-Rough 6/16/2020 Approved DAVID CHAN
Service/Power Release 6/25/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Final 7/13/2020 Not Ready for Inspection DAVID CHAN
Service/Power Release 7/13/2020 Approved DAVID CHAN
Drywall Nailing 7/20/2020 Approved DAVID CHAN
ELECTRICAL-Final 7/20/2020 Approved DAVID CHAN
Final 7/20/2020 Corrections Issued DAVID CHAN
Green Building Final 7/20/2020 Approved DAVID CHAN
HVAC-Final 7/20/2020 Approved DAVID CHAN
PLUMBING-Final 7/20/2020 Not Ready for Inspection DAVID CHAN
SGSOV-Seismic Gas S/O Valve 7/20/2020 SGSOV Approved DAVID CHAN
Smoke Detectors 7/20/2020 Approved DAVID CHAN
ELECTRICAL-Final 9/4/2020 Approved DAVID CHAN
Final 9/4/2020 Not Ready for Inspection DAVID CHAN
HVAC-Final 9/4/2020 Approved DAVID CHAN
PLUMBING-Final 9/4/2020 Approved DAVID CHAN
Final 9/23/2020 OK to Issue CofO DAVID CHAN