15537 W CHASE ST 91343
Certificate Information: 15537 W CHASE ST 91343
- Application / Permit
- 20016-20000-03398
- Plan Check / Job No.
- B20VN01892
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 2/13/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2020 | ALDOUS CHIC |
| Corrections Issued | 2/5/2020 | ALDOUS CHIC |
| Plan Check Approved | 2/13/2020 | PINANK PATEL |
| Issued | 2/13/2020 | LADBS |
| CofO in Progress | 12/7/2020 | GREGG CUMMINGS |
| CofO Issued | 5/8/2021 | MICHAEL SMITH |
| Permit Finaled | 5/8/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/5/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/5/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/11/2020 | Partial Approval | BEAU COLLINS |
| Footing/Foundation/Slab | 8/17/2020 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2020 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 8/31/2020 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/31/2020 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 8/31/2020 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/31/2020 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/9/2020 | Approved | GREGG CUMMINGS |
| Green Building Rough | 9/9/2020 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 9/9/2020 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/9/2020 | Approved | GREGG CUMMINGS |
| MERV13>=Rough | 9/9/2020 | Approved | GREGG CUMMINGS |
| Insulation | 9/14/2020 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 9/18/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/25/2020 | Approved | GREGG CUMMINGS |
| Sewer | 9/25/2020 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/2/2020 | Approved | GREGG CUMMINGS |
| Final | 10/13/2020 | Corrections Issued | WILLIAM KUEHN |
| Green Building Final | 10/13/2020 | Approved | WILLIAM KUEHN |
| MERV13>=Final | 10/13/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 10/13/2020 | SGSOV Approved | WILLIAM KUEHN |
| Smoke Detectors | 10/13/2020 | Approved | WILLIAM KUEHN |
| Final | 10/22/2020 | Partial Inspection | GREGG CUMMINGS |
| Final | 10/29/2020 | Partial Inspection | GREGG CUMMINGS |
| Service/Power Release | 10/29/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 11/4/2020 | Corrections Issued | GREGG CUMMINGS |
| Final | 11/12/2020 | Partial Inspection | GREGG CUMMINGS |
| Final | 12/2/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 12/7/2020 | Approved | GREGG CUMMINGS |
| Final | 12/7/2020 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 12/7/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 12/7/2020 | Approved | GREGG CUMMINGS |