7023 N JELLICO AVE 91406
Certificate Information: 7023 N JELLICO AVE 91406
- Application / Permit
- 20016-20000-02895
- Plan Check / Job No.
- B20VN01611
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert the detached garage into an Accessory Dwelling Unit
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2020 | ANGELICA DAVE |
| Corrections Issued | 1/31/2020 | ANGELICA DAVE |
| Plan Check Approved | 1/31/2020 | JEFFREY TANGONAN |
| Issued | 2/5/2020 | LADBS |
| CofO in Progress | 6/22/2021 | STEVEN BACK |
| Permit Finaled | 6/23/2021 | JOHN JANSON |
| CofO Issued | 6/23/2021 | JOHN JANSON |
| Permit Finaled | 6/23/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 1/31/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/23/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 3/23/2021 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 3/31/2021 | Not Ready for Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 3/31/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 3/31/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 3/31/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 4/9/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 4/9/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 4/9/2021 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 4/22/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2021 | Approved | STEVEN BACK |
| Green Building Rough | 4/22/2021 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 4/22/2021 | Approved | STEVEN BACK |
| Insulation | 4/22/2021 | Partial Approval | STEVEN BACK |
| Interior/Exterior Lathing | 4/22/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 4/22/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 4/27/2021 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 4/27/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 4/27/2021 | Approved | CALEB MEISTER |
| Shower Pan | 4/27/2021 | Not Ready for Inspection | CALEB MEISTER |
| Drywall Nailing | 5/4/2021 | Approved | DAVID SCANTLIN |
| Shower Pan | 5/4/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 6/14/2021 | Approved | STEVEN BACK |
| Final | 6/14/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 6/14/2021 | Approved | STEVEN BACK |
| Green Building Rough | 6/14/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/14/2021 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 6/14/2021 | Approved | STEVEN BACK |
| Final | 6/22/2021 | OK to Issue CofO | STEVEN BACK |