6924 N ENCINO AVE 91406
Certificate Information: 6924 N ENCINO AVE 91406
- Application / Permit
- 20016-20000-02750
- Plan Check / Job No.
- B20VN01531
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert the detached garage and workshop into an Accessory Dwelling Unit
- Permit Issued
- Issued on 6/29/2020
- Issuing Office
- Current Status
- CofO Issued on 10/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | ANGELICA DAVE |
| Corrections Issued | 1/30/2020 | ANGELICA DAVE |
| Plan Check Approved | 6/29/2020 | JEROME MAGAT PALMA |
| Issued | 6/29/2020 | APPLICANT |
| CofO in Progress | 10/13/2020 | STEVEN BACK |
| CofO Issued | 10/19/2020 | MICHAEL SMITH |
| Permit Finaled | 10/19/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/30/2020 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2020 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 1/30/2020 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/6/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 7/6/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 7/6/2020 | Corrections Issued | STEVEN BACK |
| Underground Mechanical | 7/6/2020 | Partial Approval | STEVEN BACK |
| Deputy Drilled-In Anchors | 7/7/2020 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 7/20/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/24/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 7/24/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/27/2020 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 7/27/2020 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 7/27/2020 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 7/30/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 7/30/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2020 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 7/30/2020 | Approved | STEVEN BACK |
| HVAC-Rough | 7/30/2020 | Approved | STEVEN BACK |
| Insulation | 8/4/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/4/2020 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2020 | Approved | STEVEN BACK |
| Shower Pan | 8/6/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 8/11/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/17/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/16/2020 | Corrections Issued | STEVEN BACK |
| Final | 9/16/2020 | Corrections Issued | STEVEN BACK |
| Green Building Final | 9/16/2020 | Approved | STEVEN BACK |
| HVAC-Final | 9/16/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Final | 9/16/2020 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 9/16/2020 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 9/16/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 9/30/2020 | Approved | STEVEN BACK |
| Final | 9/30/2020 | Corrections Issued | STEVEN BACK |
| HVAC-Final | 9/30/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Final | 9/30/2020 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 9/30/2020 | SGSOV Approved | STEVEN BACK |
| Final | 10/8/2020 | Corrections Issued | STEVEN BACK |
| HVAC-Final | 10/8/2020 | Not Ready for Inspection | STEVEN BACK |
| Final | 10/13/2020 | OK to Issue CofO | STEVEN BACK |
| HVAC-Final | 10/13/2020 | Approved | STEVEN BACK |