17220-17222 W SIMONDS ST 91344

Certificate Information: 17220-17222 W SIMONDS ST 91344

Application / Permit
20016-20000-02733
Plan Check / Job No.
B20VN01519
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert the attached garage and portion of the single-family dwelling into an irregular 17'11" x 33'4" Accessory Dwelling Unit.
Permit Issued
Issued on 2/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 ANGELICA DAVE
Corrections Issued 1/30/2020 ANGELICA DAVE
Plan Check Approved 2/5/2020 LUIS RINCON
Issued 2/5/2020 LADBS
CofO in Progress 7/19/2022 DAVID SCANTLIN
Permit Finaled 7/21/2022 JOHN JANSON
CofO Issued 7/21/2022 JOHN JANSON
Permit Finaled 7/21/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/30/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 1/30/2020 MANUEL TEJADA
Sewer availability Cleared 1/30/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/5/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Boules,, George Helmy; Lic. No.: C64144 20016 LULL ST      WINNETKA, CA 91306

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/25/2020 Approved DAVID SCANTLIN
PLUMBING-Rough 3/3/2020 Approved DAVID SCANTLIN
Sewer 3/3/2020 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/23/2020 Approved DAVID SCANTLIN
ELECTRICAL-Rough 3/23/2020 Approved DAVID SCANTLIN
Green Building Rough 3/23/2020 Not Ready for Inspection DAVID SCANTLIN
MERV13>=Rough 3/23/2020 Approved DAVID SCANTLIN
HVAC-Rough 3/24/2020 Approved DAVID SCANTLIN
HVAC-Rough 4/3/2020 Approved DAVID SCANTLIN
Drywall Nailing 4/16/2020 Approved DAVID SCANTLIN
Shower Pan 4/16/2020 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 5/29/2020 Approved DAVID SCANTLIN
Final 5/29/2020 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 5/29/2020 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 5/29/2020 Approved DAVID SCANTLIN
MERV13>=Final 5/29/2020 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 5/29/2020 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 5/29/2020 Approved DAVID SCANTLIN
Final 6/3/2020 Partial Approval DAVID SCANTLIN
Green Building Final 6/3/2020 Approved DAVID SCANTLIN
Final 6/22/2022 Corrections Issued DAVID SCANTLIN
Final 7/18/2022 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 7/18/2022 Approved DAVID SCANTLIN