2209 S GLENCOE AVE 90291

Certificate Information: 2209 S GLENCOE AVE 90291

Application / Permit
20016-20000-02515
Plan Check / Job No.
B20VN01412
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 11'-4" X 26'-6" DETACHED RECREATION ROOM/LAUNDRY ROOM TO A (N) ACCESSORY DWELLING UNIT (300 SQ FT), (E) GARAGE TO REMAIN W/ NEW LAUNDRY UNITS AND WET BAR. ALL WORK PER WFPP.
Permit Issued
Issued on 2/28/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2020 APPLICANT
Assigned to Plan Check Engineer 2/3/2020 JENNIFER LEE
Corrections Issued 2/3/2020 JENNIFER LEE
Applicant returned to address corrections 2/13/2020 ANGELICA DAVE
Plan Check Approved 2/14/2020 JEROME MAGAT PALMA
Issued 2/28/2020 LADBS
CofO in Progress 3/15/2025 DAVID FEILER
Permit Finaled 3/17/2025 RICHARD STEINBACH
CofO Issued 3/17/2025 RICHARD STEINBACH
Permit Finaled 3/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 2/4/2020 PABLO ESTRADA
Specific Plan Cleared 2/10/2020 FREDDY GARCIA
Address approval Cleared 2/12/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/12/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/12/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Blackfox; Lic. No.: 788491-B 4918 W 138TH STREET      HAWTHORNE, CA 90250

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 3/25/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 4/2/2020 Partial Approval DAVID HEINE
Underground Mechanical 4/2/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 4/8/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 4/17/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 4/17/2020 Approved DAVID HEINE
Green Building Rough 4/17/2020 Approved DAVID HEINE
HVAC-Rough 4/17/2020 Approved DAVID HEINE
PLUMBING-Rough 4/17/2020 Approved DAVID HEINE
Interior/Exterior Lathing 4/22/2020 Partial Approval DAVID HEINE
Insulation 4/23/2020 Approved DAVID HEINE
Drywall Nailing 4/28/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 6/16/2020 Approved DAVID HEINE
Final 6/16/2020 Conditional Approval DAVID HEINE
Green Building Final 6/16/2020 Approved DAVID HEINE
Smoke Detectors 6/16/2020 Approved DAVID HEINE
Final 9/10/2020 Conditional Approval DAVID HEINE
Final 3/15/2025 OK to Issue CofO DAVID FEILER