1724 S SHENANDOAH ST 90035

Certificate Information: 1724 S SHENANDOAH ST 90035

Application / Permit
20016-20000-02369
Plan Check / Job No.
B20VN01339
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-6" X 22'-0" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/27/2020
Issuing Office
Current Status
CofO Issued on 7/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2020 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 JENNIFER LEE
Corrections Issued 1/30/2020 JENNIFER LEE
Applicant returned to address corrections 2/5/2020 ANGELICA DAVE
Plan Check Approved 5/8/2020 RAPHAEL ROSAS
Issued 5/27/2020 APPLICANT
Building Plans Picked Up 5/27/2020 APPLICANT
CofO in Progress 7/7/2022 EVAN COOPER
Permit Finaled 7/13/2022 KENNETH NAGLE
CofO Issued 7/13/2022 KENNETH NAGLE
Permit Finaled 7/13/2022 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 2/3/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/3/2020 THOMAS LANG
Sewer availability Cleared 2/3/2020 THOMAS LANG
Construction near power lines Cleared 4/27/2020 RIDWAN HARDY

Contact Information

Contractor A R M Builders Inc; Lic. No.: 915352-B 1080 S LA CIENEGA #311      LOS ANGELES, CA 90035
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 12/2/2020 Corrections Issued EVAN COOPER
Pre-Inspection 5/25/2021 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 7/9/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 7/16/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 8/6/2021 Partial Approval EVAN COOPER
Green Building Rough 8/6/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 8/6/2021 Approved EVAN COOPER
Interior/Exterior Lathing 8/19/2021 Corrections Issued SHAVONNE ESPINOZA
Interior/Exterior Lathing 8/24/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 9/14/2021 Corrections Issued EVAN COOPER
PLUMBING-Rough 9/14/2021 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 9/23/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Approved EVAN COOPER
Green Building Rough 9/23/2021 Approved EVAN COOPER
Wood Frame 9/23/2021 Approved EVAN COOPER
Insulation 10/4/2021 Conditional Approval EVAN COOPER
Drywall Nailing 10/20/2021 Approved KRISTEN CAUSEY
Final 3/15/2022 Corrections Issued EVAN COOPER
Green Building Final 3/15/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 3/15/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 3/15/2022 Approved EVAN COOPER
Final 4/14/2022 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Final 7/7/2022 Approved EVAN COOPER
Final 7/7/2022 OK to Issue CofO EVAN COOPER
HVAC-Final 7/7/2022 Approved EVAN COOPER
PLUMBING-Final 7/7/2022 Approved EVAN COOPER