12360-12362 N JOLETTE AVE 91344

Certificate Information: 12360-12362 N JOLETTE AVE 91344

Application / Permit
20016-20000-02318
Plan Check / Job No.
B20VN01304
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20' X 24' ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER WFPP. "COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 12/27/19. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
Permit Issued
Issued on 2/14/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/7/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2020 APPLICANT
Assigned to Plan Check Engineer 1/29/2020 JENNIFER LEE
Corrections Issued 1/29/2020 JENNIFER LEE
Application Withdrawn-Void 2/14/2020 OMID HEDAYAT
Re-Activate Application 2/14/2020 OMID HEDAYAT
Plan Check Approved 2/14/2020 ANGELICA MARTINEZ
Issued 2/14/2020 LADBS
CofO in Progress 8/5/2020 HAGOP BADOSSIAN
CofO Issued 8/7/2020 ROBERT GOLD
Permit Finaled 8/7/2020 ROBERT GOLD

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/13/2020 KIRK LINKLATER
Address approval Cleared 2/14/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/14/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/14/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor E G N Builders Group; Lic. No.: 1051430-B 5901 LINDERO CYN RD BLD 2   STE 2-200    WESTLAKE VILLAGE, CA 91362

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/25/2020 Approved HAGOP BADOSSIAN
Deputy Drilled-In Anchors 4/15/2020 Conditional Approval HAGOP BADOSSIAN
Excavation/Setback/Form/Re-Bar 4/15/2020 Approved HAGOP BADOSSIAN
Footing/Foundation/Slab 4/15/2020 Approved HAGOP BADOSSIAN
BUILDING-Rough-Frame 5/22/2020 Partial Inspection ROBERT GOLD
ELECTRICAL-Rough 5/22/2020 Partial Inspection ROBERT GOLD
Green Building Rough 5/22/2020 Partial Inspection ROBERT GOLD
HVAC-Rough 5/22/2020 Partial Inspection ROBERT GOLD
PLUMBING-Rough 5/22/2020 Partial Inspection ROBERT GOLD
Rough-Elec/Plmb/HVAC 5/22/2020 Partial Inspection ROBERT GOLD
BUILDING-Rough-Frame 5/28/2020 Approved HAGOP BADOSSIAN
ELECTRICAL-Rough 5/28/2020 Approved HAGOP BADOSSIAN
Floor/Roof Diaphrgm/Shear Wall 5/28/2020 Approved HAGOP BADOSSIAN
Green Building Rough 5/28/2020 Approved HAGOP BADOSSIAN
Insulation 5/28/2020 Approved HAGOP BADOSSIAN
PLUMBING-Rough 5/28/2020 Approved HAGOP BADOSSIAN
Underground Mechanical 5/28/2020 Partial Approval HAGOP BADOSSIAN
Drywall Nailing 6/4/2020 Approved HAGOP BADOSSIAN
Final 7/2/2020 Corrections Issued MARK DOVICO
Green Building Final 7/2/2020 Approved MARK DOVICO
SGSOV-Seismic Gas S/O Valve 7/2/2020 SGSOV Approved MARK DOVICO
Sewer 7/2/2020 Approved MARK DOVICO
Smoke Detectors 7/2/2020 Approved MARK DOVICO
Final 7/7/2020 Not Ready for Inspection HAGOP BADOSSIAN
MERV13>=Final 7/7/2020 Approved HAGOP BADOSSIAN
SWPPP-Const. Storm Water 7/7/2020 Not Required HAGOP BADOSSIAN
Service/Power Release 7/7/2020 Approved HAGOP BADOSSIAN
Final 7/9/2020 Corrections Issued HAGOP BADOSSIAN
Final 8/4/2020 OK to Issue CofO HAGOP BADOSSIAN