4849 N BECK AVE 91601
Certificate Information: 4849 N BECK AVE 91601
- Application / Permit
- 20016-20000-02273
- Plan Check / Job No.
- B20VN01280
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert the (e) 19' x 18'9" irregular shapped workshop into an Accessory Dwelling Unit , all work per engineering
- Permit Issued
- Issued on 6/19/2020
- Issuing Office
- Current Status
- CofO Issued on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2020 | ANGELICA DAVE |
| Corrections Issued | 1/27/2020 | ANGELICA DAVE |
| Applicant returned to address corrections | 2/18/2020 | LUIS RINCON |
| Plan Check Approved | 2/19/2020 | RARES BODEA |
| Issued | 6/19/2020 | APPLICANT |
| CofO in Progress | 8/20/2021 | THOMAS FINNILA |
| CofO in Progress | 8/20/2021 | THOMAS FINNILA |
| Permit Finaled | 5/4/2022 | MICHAEL SMITH |
| CofO Issued | 5/4/2022 | MICHAEL SMITH |
| Permit Finaled | 5/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/27/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/27/2020 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 1/27/2020 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 1/28/2020 | RIDWAN HARDY |
| Specific Plan | Cleared | 1/29/2020 | OLGA AYALA |
Contact Information
| Architect | Brash,, Victoria A; Lic. No.: C36403 | 4650 FARMDALE AVENUE NORTH HOLLYWOOD, CA 91602 |
| Contractor | The Masters Shop Construction Inc; Lic. No.: 1028534-B | 17740 SHERMAN WAY RESEDA, CA 91335 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 6/22/2020 | Corrections Issued | THOMAS FINNILA |
| Sewer | 6/22/2020 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/29/2020 | Not Ready for Inspection | BEAU COLLINS |
| Gas Test | 6/29/2020 | Approved | BEAU COLLINS |
| PLUMBING-Rough | 6/29/2020 | Approved | BEAU COLLINS |
| Sewer | 6/29/2020 | Approved | BEAU COLLINS |
| ELECTRICAL-Final | 8/19/2020 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/19/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 8/19/2020 | Corrections Issued | THOMAS FINNILA |
| Wood Frame | 8/19/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/24/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 8/24/2020 | Corrections Issued | THOMAS FINNILA |
| Wood Frame | 8/24/2020 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/28/2020 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 8/28/2020 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 8/28/2020 | Approved | THOMAS FINNILA |
| HVAC-Rough | 8/28/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/28/2020 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 8/28/2020 | Approved | THOMAS FINNILA |
| HVAC-Final | 9/3/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 9/3/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/3/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Drywall Nailing | 9/10/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 9/10/2020 | Approved | DANIEL DREW |
| Shower Pan | 9/10/2020 | Approved | DANIEL DREW |
| Shower Pan | 9/21/2020 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/21/2021 | Approved | THOMAS FINNILA |
| Final | 5/21/2021 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 5/21/2021 | Corrections Issued | THOMAS FINNILA |
| MERV13>=Final | 5/21/2021 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/21/2021 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 5/21/2021 | Approved | THOMAS FINNILA |
| Final | 7/30/2021 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 7/30/2021 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/30/2021 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 8/19/2021 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 8/19/2021 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/19/2021 | SGSOV Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 9/29/2021 | Approved | THOMAS FINNILA |
| Service/Power Release | 11/2/2021 | Approved | THOMAS FINNILA |