7218-7220 N RUBIO AVE 91406

Certificate Information: 7218-7220 N RUBIO AVE 91406

Application / Permit
20016-20000-02260
Plan Check / Job No.
B20VN01269
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER DESIGN
Permit Issued
Issued on 1/27/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2020 APPLICANT
Assigned to Plan Check Engineer 1/27/2020 ALDOUS CHIC
Corrections Issued 1/27/2020 ALDOUS CHIC
Plan Check Approved 1/27/2020 ANGELICA MARTINEZ
Issued 1/27/2020 LADBS
CofO in Progress 12/29/2020 ARTHUR SARGSYAN
CofO Issued 2/13/2021 MICHAEL SMITH
Permit Finaled 2/13/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/27/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/27/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/27/2020 JOHN TRIANTAFYLLOS

Contact Information

Architect Tohill,, Kevin Patrick; Lic. No.: C32787 3790 LIGHTNING RIDGE WAY      SIMI VALLEY, CA 93063
Contractor Gabe Kaprelian Electrical Contractor; Lic. No.: 321040-B 7220 RUBIO AVE      VAN NUYS, CA 91406

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/1/2020 Partial Approval DANIEL DREW
Sewer 7/1/2020 Approved DANIEL DREW
BUILDING-Rough-Frame 7/8/2020 Corrections Issued DANIEL DREW
Green Building Rough 7/8/2020 Not Ready for Inspection DANIEL DREW
Footing/Foundation/Slab 7/16/2020 Approved DANIEL DREW
Drywall Nailing 7/30/2020 Approved DANIEL DREW
Drywall Nailing 8/4/2020 Approved DANIEL ORRANTE
BUILDING-Rough-Frame 9/28/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 9/28/2020 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Approved JENNIFER RABUCHIN
Gas Test 9/28/2020 Partial Approval JENNIFER RABUCHIN
Green Building Rough 9/28/2020 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 9/28/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 9/28/2020 Approved JENNIFER RABUCHIN
Insulation 10/9/2020 Conditional Approval MICHAEL TEMPLE
Underground Mechanical 10/9/2020 Approved MICHAEL TEMPLE
Drywall Nailing 11/5/2020 Approved ARTHUR SARGSYAN
Green Building Rough 11/5/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 11/5/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 12/15/2020 Not Ready for Inspection JOHN HAYES
Final 12/15/2020 Not Ready for Inspection JOHN HAYES
Green Building Final 12/15/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 12/15/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 12/15/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 12/22/2020 Approved ARTHUR SARGSYAN
Final 12/22/2020 OK to Issue CofO ARTHUR SARGSYAN
Green Building Final 12/22/2020 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/22/2020 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 12/22/2020 Approved ARTHUR SARGSYAN