4654 N VANTAGE AVE 91607

Certificate Information: 4654 N VANTAGE AVE 91607

Application / Permit
20016-20000-02109
Plan Check / Job No.
B20VN01187
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert the detached garage into an Accessory Dwelling Unit
Permit Issued
Issued on 1/28/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Assigned to Plan Check Engineer 1/24/2020 ANGELICA DAVE
Corrections Issued 1/24/2020 ANGELICA DAVE
Plan Check Approved 1/27/2020 ANGELICA MARTINEZ
Issued 1/28/2020 LADBS
CofO in Progress 5/12/2022 ARAM AVEDISIAN
Permit Finaled 5/12/2022 MICHAEL SMITH
CofO Issued 5/12/2022 MICHAEL SMITH
Permit Finaled 5/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/24/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/24/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/24/2020 JOHN TRIANTAFYLLOS
Specific Plan Cleared 1/24/2020 DANIEL SKOLNICK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/31/2020 Not Ready for Inspection ARAM AVEDISIAN
Final 1/31/2020 Not Ready for Inspection ARAM AVEDISIAN
Green Building Final 1/31/2020 No Access for Inspection ARAM AVEDISIAN
Green Building Rough 1/31/2020 Not Ready for Inspection ARAM AVEDISIAN
MERV13>=Final 1/31/2020 Not Ready for Inspection ARAM AVEDISIAN
MERV13>=Rough 1/31/2020 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/31/2020 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 1/31/2020 Not Ready for Inspection ARAM AVEDISIAN
Insulation 2/3/2020 Not Ready for Inspection JEFFREY PARD
PLUMBING-Final 2/7/2020 Corrections Issued RAYMOND KEHOE
Pre-Inspection 2/10/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 2/13/2020 Partial Approval ARAM AVEDISIAN
Sewer 2/13/2020 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 2/14/2020 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 2/18/2020 Approved ARAM AVEDISIAN
Green Building Rough 2/18/2020 Approved ARAM AVEDISIAN
MERV13>=Rough 2/18/2020 Approved ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 2/18/2020 Approved ARAM AVEDISIAN
Insulation 2/19/2020 Approved ARAM AVEDISIAN
Drywall Nailing 2/20/2020 Approved ARAM AVEDISIAN
Shower Pan 2/20/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 2/21/2020 Approved ARAM AVEDISIAN
Final 3/9/2020 Corrections Issued ARAM AVEDISIAN
Green Building Final 3/9/2020 Approved ARAM AVEDISIAN
MERV13>=Final 3/9/2020 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/9/2020 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 3/9/2020 Approved ARAM AVEDISIAN
ELECTRICAL-Final 3/12/2020 Approved RAYMOND KEHOE
Final 3/12/2020 Not Ready for Inspection RAYMOND KEHOE
HVAC-Final 3/12/2020 Approved RAYMOND KEHOE
PLUMBING-Final 3/12/2020 Approved RAYMOND KEHOE
Final 5/12/2022 OK to Issue CofO ARAM AVEDISIAN