8528-8530 N NESTLE AVE 91325
Certificate Information: 8528-8530 N NESTLE AVE 91325
- Application / Permit
- 20016-20000-02100
- Plan Check / Job No.
- B20VN01179
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert the attached garage into an Accessory Dwelling Unit
- Permit Issued
- Issued on 1/31/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/16/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2020 | ANGELICA DAVE |
| Corrections Issued | 1/24/2020 | ANGELICA DAVE |
| Plan Check Approved | 1/31/2020 | ARTIN ZARUKIAN |
| Issued | 1/31/2020 | LADBS |
| CofO in Progress | 9/16/2020 | JEFFREY PARD |
| Permit Finaled | 9/16/2020 | JOHN JANSON |
| CofO Issued | 9/16/2020 | JOHN JANSON |
| Permit Finaled | 9/16/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2020 | ADRIAN CASTRO |
| Permit | Cleared | 1/24/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/24/2020 | ADRIAN CASTRO |
| Trees in Parkway | Cleared | 1/27/2020 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chu,, Tien Manh; Lic. No.: C72324 | 9542 PACIFIC AVE ANAHEIM, CA 92804 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/4/2020 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 3/11/2020 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2020 | Partial Approval | HENRY KIM |
| Insulation | 3/31/2020 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 3/31/2020 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 4/3/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 4/9/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/9/2020 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 4/17/2020 | Not Ready for Inspection | DONALD SUNSERI |
| PLUMBING-Rough | 4/21/2020 | Partial Approval | DONALD SUNSERI |
| ELECTRICAL-Rough | 5/4/2020 | Partial Inspection | DONALD SUNSERI |
| ELECTRICAL-Rough | 5/12/2020 | Approved | DONALD SUNSERI |
| PLUMBING-Rough | 5/12/2020 | Approved | DONALD SUNSERI |
| Gas Test | 6/9/2020 | Partial Approval | DAVID SCANTLIN |
| HVAC-Rough | 6/9/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 6/10/2020 | Partial Approval | DONALD SUNSERI |
| Green Building Rough | 6/10/2020 | Approved | DONALD SUNSERI |
| HVAC-Rough | 6/10/2020 | Approved | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2020 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/19/2020 | Corrections Issued | JEFFREY PARD |
| Wood Frame | 6/19/2020 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/23/2020 | Approved | JEFFREY PARD |
| Drywall Nailing | 7/1/2020 | Approved | JEFFREY PARD |
| Gas Test | 7/28/2020 | Not Ready for Inspection | JEFFREY PARD |
| Service/Power Release | 7/28/2020 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/25/2020 | Approved | JEFFREY PARD |
| Final | 8/25/2020 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 8/25/2020 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 8/25/2020 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 8/25/2020 | Approved | JEFFREY PARD |
| Final | 9/1/2020 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 9/1/2020 | Not Ready for Inspection | JEFFREY PARD |
| Final | 9/15/2020 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 9/15/2020 | Approved | JEFFREY PARD |