23395-23397 W SCHOOLCRAFT ST 91307

Certificate Information: 23395-23397 W SCHOOLCRAFT ST 91307

Application / Permit
20016-20000-02090
Plan Check / Job No.
B20VN01174
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert the attached garage into an Accessory Dwelling Unit.
Permit Issued
Issued on 2/21/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Assigned to Plan Check Engineer 1/24/2020 ANGELICA DAVE
Corrections Issued 1/24/2020 ANGELICA DAVE
Plan Check Approved 1/24/2020 PINANK PATEL
Issued 2/21/2020 LADBS
CofO in Progress 8/11/2020 TROY SANDERS
Permit Finaled 9/8/2020 JOHN JANSON
CofO Issued 9/8/2020 JOHN JANSON
Permit Finaled 9/8/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/24/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/24/2020 ADRIAN CASTRO
Sewer availability Cleared 1/24/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/28/2020 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 3/16/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 3/19/2020 Approved JOHN KIDWELL
PLUMBING-Rough 3/19/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 4/9/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 4/24/2020 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 4/29/2020 Approved JOHN KIDWELL
ELECTRICAL-Rough 4/29/2020 Approved JOHN KIDWELL
Green Building Rough 4/29/2020 Approved JOHN KIDWELL
HVAC-Rough 4/29/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 4/29/2020 Approved JOHN KIDWELL
Drywall Nailing 5/22/2020 Approved JOHN KIDWELL
Final 7/20/2020 Corrections Issued TROY SANDERS
Green Building Final 7/20/2020 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/20/2020 SGSOV Approved TROY SANDERS
Smoke Detectors 7/20/2020 Corrections Issued TROY SANDERS
ELECTRICAL-Final 8/6/2020 Approved TROY SANDERS
Final 8/6/2020 Not Ready for Inspection TROY SANDERS
Green Building Final 8/6/2020 Approved TROY SANDERS
HVAC-Final 8/6/2020 Approved TROY SANDERS
PLUMBING-Final 8/6/2020 Approved TROY SANDERS
Smoke Detectors 8/6/2020 Approved TROY SANDERS
Final 8/11/2020 OK to Issue CofO TROY SANDERS